Deletions are marked like this. | Additions are marked like this. |
Line 8: | Line 8: |
Date: 2021/7/9 13:00-14:00 | Date: 2021/7/16 13:00-13:35 |
Line 10: | Line 10: |
Participants: Takahashi, Ikeda, Sato, Ushiba, Kimura, Aso, Tomaru, Node, Hirata | Participants: Takahashi, Node, Ikeda, Ushiba, Tomaru, Sato, Aso, Kimura, Miyo |
Line 15: | Line 15: |
* IX: To the finalization. * EX: Alignment for the green beam was finished. To the finalization * IY: Height adjustment is on going. * EY: Mirror cleaning is on going in Mitaka. Measurement system had a problem. The shipping will be in the end of next week at earliest. |
* IX: Still some cabling from payload have problems. To the finalization. * EX: Aligned for the green beam again. To the finalization * IY: F1 was recovered. Adjustable range of F0 was extended ([[https://www.dropbox.com/s/a8p7m6luxz6ndwn/Height%20range%20rev.pdf?dl=0|Height range]]). Range of BF damper should be taken into account. The height adjustment was scheduled in the week of 7/26. * EY: Mirror cleaning was almost finished. The shipping will be in the next week (transported after holidays). |
Line 21: | Line 21: |
* Corrugate tube fixing jig: Implementation is scheduled on 7/12-13. | * Corrugate tube fixing jig: Replaced on 7/12-13. |
Line 23: | Line 23: |
* Commissioning in air: X-arm. | * Commissioning in air: on going in X-arm. Oplev calibration is necessary. |
Line 28: | Line 28: |
* Separation of rack in 2F: This is scheduled on 7/16. * New vacuum pumps for V-chambers: Considering the port location. * Extension of cables for picomotor drivers: Tested in EYV. |
* Separation of rack in 2F: It was finished on 7/16. * New vacuum pumps for V-chambers: Problem on the support for GVs. |
Line 33: | Line 32: |
Adjustable height range of the filter chain in IY * [[https://www.dropbox.com/s/i7e0grqv324sdfz/Height%20range.pdf?dl=0|Present height range]] * The condition of F1 stepper motor is the same as the F3 in IX. We tried to move the motor with the stand alone driver, but the FR is still not working. * The motor is still not working? * The FR slider is stuck? * The range of BF is too small. Check the mechanical stopper. * Tune the F0 more to lower frequency (now 0.4Hz) in order to extend the range. |
---------- = VIS Meeting = 14:00- |
Line 41: | Line 36: |
== Next meeting == * 2021/7/16(FRI) |
Participants: |
Line 45: | Line 39: |
'''EX''' * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17376|17376]] ETMX IM dewhitening filters and comb60 filters are implemented , __takafumi.ushiba__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17396|17396]] Oplev preparation at EXC , __takaaki.yokozawa__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17450|17450]] Oplev calibration EX TM oplev , __takaaki.yokozawa__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17496|17496]] ETMX IM photosensor trouble shooting , __takafumi.ushiba__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17503|17503]] Rebooter installation for pico motor drivers. (ETMX) , __koji.nakagaki__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17506|17506]] Replacement of fixing jigs for the corrugate tube , __ryutaro.takahashi__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17267|17267]] Oplev preparation work EX , __takaaki.yokozawa__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17362|17362]] Comment , __takaaki.yokozawa__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17358|17358]] Injection of OpLev lasers to the cryostat at EXC , __takafumi.ushiba__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17361|17361]] Comment , __takaaki.yokozawa__ '''EY''' * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17457|17457]] dial gauge installation, Pico motor cable extension test , __naohisa.satou__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17485|17485]] Replacement of fixing jigs for the corrugate tube , __ryutaro.takahashi__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17485|17485]] Replacement of fixing jigs for the corrugate tube , __ryutaro.takahashi__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17505|17505]] Comment , __ryutaro.takahashi__ '''General''' * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17369|17369]] Added EPICS channel for VIS temperature adjustment , __satoru.ikeda__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17368|17368]] Implemented some Oplev-related fixes to the VIS model file. , __satoru.ikeda__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17388|17388]] Implementation of sensor to EULER matrix for IM photosensors , __takafumi.ushiba__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17455|17455]] TypeA,B,Bp VIS Guardian changed to SAFE , __satoru.ikeda__ * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17513|17513]] Safe.snap of MCi,e,o are updated after Miyoki-san closed laser shutter. , __kouseki.miyo__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17079|17079]] Organizing DAQ channels for VIS , __satoru.ikeda__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17460|17460]] Comment , __satoru.ikeda__ '''IX''' * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17400|17400]] Modification of damp_temp filter for MN DAMP filter of ITMX , __takafumi.ushiba__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17405|17405]] IX Pico motor driver was broken and replaced. , __koji.nakagaki__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17449|17449]] Oplev calibration IX TM oplevs , __takaaki.yokozawa__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17468|17468]] MNH1 actuator of ITMX seems to have an issue. , __takafumi.ushiba__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17482|17482]] Re-calibration of the IX TM length oplev , __takaaki.yokozawa__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17481|17481]] ITMX MNH1 cable repairement , __takafumi.ushiba__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17247|17247]] Rebooter installation for pico motor drivers. (ITMX) , __koji.nakagaki__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17502|17502]] Comment , __koji.nakagaki__ * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17522|17522]] Comment , __koji.nakagaki__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17335|17335]] Checked resistance of TF and BF LVDT actuators coil. , __naohisa.satou__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17367|17367]] Comment , __naohisa.satou__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17377|17377]] Comment , __ryutaro.takahashi__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17405|17405]] IX Pico motor driver was broken and replaced. , __koji.nakagaki__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17420|17420]] Comment , __satoru.ikeda__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17449|17449]] Oplev calibration IX TM oplevs , __takaaki.yokozawa__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17461|17461]] Comment , __takafumi.ushiba__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17469|17469]] Comment , __takafumi.ushiba__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17497|17497]] Comment , __kouseki.miyo__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17468|17468]] MNH1 actuator of ITMX seems to have an issue. , __takafumi.ushiba__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17472|17472]] Comment , __takafumi.ushiba__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17481|17481]] ITMX MNH1 cable repairement , __takafumi.ushiba__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17501|17501]] Comment , __takafumi.ushiba__ * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17516|17516]] Comment , __takafumi.ushiba__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17482|17482]] Re-calibration of the IX TM length oplev , __takaaki.yokozawa__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17488|17488]] Comment , __takafumi.ushiba__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=8564|8564]] ITMX healthy check after pump down , __lucia.trozzo__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17366|17366]] Comment , __kouseki.miyo__ '''IY''' * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17406|17406]] Setup of pre-isolator , __ryutaro.takahashi__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17484|17484]] Replacement of fixing jigs for the corrugate tube , __ryutaro.takahashi__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17406|17406]] Setup of pre-isolator , __ryutaro.takahashi__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17431|17431]] Comment , __ryutaro.takahashi__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17441|17441]] Comment , __ryutaro.takahashi__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17498|17498]] Comment , __naohisa.satou__ * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17526|17526]] Comment , __ryutaro.takahashi__ '''MCE''' * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17523|17523]] About the placement of the mini-rack in MCE , __koji.nakagaki__ '''PR2''' * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17478|17478]] Rotate PR2 mirror by IM_YAW picomotor but we had better to use traverser , __kouseki.miyo__ * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17520|17520]] PR2 Traversor motor and PR2 IM PITCH drive Picomotor , __satoru.ikeda__ '''SR2''' * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17434|17434]] Cable connection check , __naoatsu.hirata__ '''SR3''' * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17439|17439]] Cable connection check , __naoatsu.hirata__ '''SRM''' * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17314|17314]] Optical lever installation , __fabian.arellano__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17372|17372]] Comment , __fabian.arellano__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17499|17499]] Comment , __terrence.tsang__ |
|
Line 49: | Line 136: |
* Adjusted the ballasts on the cryo-payload and the BF in IY. Additional spring was implemented on the BF. * Repaired the broken cables for TF/BF actuator opening the chamber. The BF and TF were recovered and the chamber was closed. |
* IY: Recovered the F1, F2 FRs. Compressed the F0 blades more to extend the height range. Total adjustable range became +/- 10.6mm. * IX: Calibrated the BF damper. The LVDT driver was replaced to the low noise one. * The corrugate tube fixing jigs were replaced in IY, EY, and EX. |
Line 53: | Line 141: |
* This week we installed SR2 oplev hardware and routed the power cable from the rack to the SLED. Next week we'll align the optical components. * On the week before the ast one, we installed the SRM oplev optics, aligned the optical components and calibrated the QPD in terms of their displacements. |
|
Line 60: | Line 151: |
* Type-A team: Adjustment of IYV | * Type-A team: Finalization of IX and EX. |
Line 81: | Line 172: |
BS Outer frame * The brace (support beam) for BS outer frame was not attached in O3. The brace itself is ready. * We have a structure analysis for the frame prototype (SR type), but not for the BS type. * I like to ask Sato-san the analysis for BS type to confirm the availability. |
|
Line 82: | Line 179: |
The week from 7/5 | The week from 7/19 |
Line 84: | Line 181: |
* Takahashi: 7/5-8 (KIW8 7/7-9) * Sato: 7/5-8 * Hirata: 7/5-9 * Yano: 7/5-9 |
* Takahashi: 7/19-21 * Sato: 7/19-21 * Hirata: 7/19-21 * Yano: 7/19-21 |
Line 89: | Line 186: |
The week from 7/12 | The week from 7/26 |
Line 91: | Line 188: |
* Takahashi: 7/12-16 * Sato: 7/12-16 * Hirata: 7/12-16 * Yano: 7/12-16 |
* Takahashi: 7/26-30 * Hirata: 7/26-30 * Yano: 7/26-30 |
Line 97: | Line 193: |
* 2021/7/16(FRI) | * 2021/7/30(FRI) |
Contents
Agenda/Minutes
CRY+VIS Interface Meeting
Date: 2021/7/16 13:00-13:35
Participants: Takahashi, Node, Ikeda, Ushiba, Tomaru, Sato, Aso, Kimura, Miyo
Schedule
- IX: Still some cabling from payload have problems. To the finalization.
- EX: Aligned for the green beam again. To the finalization
IY: F1 was recovered. Adjustable range of F0 was extended (Height range). Range of BF damper should be taken into account. The height adjustment was scheduled in the week of 7/26.
- EY: Mirror cleaning was almost finished. The shipping will be in the next week (transported after holidays).
Status
- Corrugate tube fixing jig: Replaced on 7/12-13.
- TM height setting: ITMY.
- Commissioning in air: on going in X-arm. Oplev calibration is necessary.
- Commissioning in vacuum:
- Overall commissioning:
- Acceptance check: Every Friday.
- PF actuator: After SC.
- Separation of rack in 2F: It was finished on 7/16.
- New vacuum pumps for V-chambers: Problem on the support for GVs.
Discussion
VIS Meeting
14:00-
Participants:
Klog
EX
17376 ETMX IM dewhitening filters and comb60 filters are implemented , takafumi.ushiba
17396 Oplev preparation at EXC , takaaki.yokozawa
17450 Oplev calibration EX TM oplev , takaaki.yokozawa
17496 ETMX IM photosensor trouble shooting , takafumi.ushiba
17503 Rebooter installation for pico motor drivers. (ETMX) , koji.nakagaki
17506 Replacement of fixing jigs for the corrugate tube , ryutaro.takahashi
17267 Oplev preparation work EX , takaaki.yokozawa
17362 Comment , takaaki.yokozawa
17358 Injection of OpLev lasers to the cryostat at EXC , takafumi.ushiba
17361 Comment , takaaki.yokozawa
EY
17457 dial gauge installation, Pico motor cable extension test , naohisa.satou
17485 Replacement of fixing jigs for the corrugate tube , ryutaro.takahashi
17485 Replacement of fixing jigs for the corrugate tube , ryutaro.takahashi
17505 Comment , ryutaro.takahashi
General
17369 Added EPICS channel for VIS temperature adjustment , satoru.ikeda
17368 Implemented some Oplev-related fixes to the VIS model file. , satoru.ikeda
17388 Implementation of sensor to EULER matrix for IM photosensors , takafumi.ushiba
17455 TypeA,B,Bp VIS Guardian changed to SAFE , satoru.ikeda
17513 Safe.snap of MCi,e,o are updated after Miyoki-san closed laser shutter. , kouseki.miyo
17079 Organizing DAQ channels for VIS , satoru.ikeda
17460 Comment , satoru.ikeda
IX
17400 Modification of damp_temp filter for MN DAMP filter of ITMX , takafumi.ushiba
17405 IX Pico motor driver was broken and replaced. , koji.nakagaki
17449 Oplev calibration IX TM oplevs , takaaki.yokozawa
17468 MNH1 actuator of ITMX seems to have an issue. , takafumi.ushiba
17482 Re-calibration of the IX TM length oplev , takaaki.yokozawa
17481 ITMX MNH1 cable repairement , takafumi.ushiba
17247 Rebooter installation for pico motor drivers. (ITMX) , koji.nakagaki
17335 Checked resistance of TF and BF LVDT actuators coil. , naohisa.satou
17405 IX Pico motor driver was broken and replaced. , koji.nakagaki
17420 Comment , satoru.ikeda
17449 Oplev calibration IX TM oplevs , takaaki.yokozawa
17468 MNH1 actuator of ITMX seems to have an issue. , takafumi.ushiba
17472 Comment , takafumi.ushiba
17481 ITMX MNH1 cable repairement , takafumi.ushiba
17482 Re-calibration of the IX TM length oplev , takaaki.yokozawa
17488 Comment , takafumi.ushiba
8564 ITMX healthy check after pump down , lucia.trozzo
17366 Comment , kouseki.miyo
IY
17406 Setup of pre-isolator , ryutaro.takahashi
17484 Replacement of fixing jigs for the corrugate tube , ryutaro.takahashi
17406 Setup of pre-isolator , ryutaro.takahashi
MCE
17523 About the placement of the mini-rack in MCE , koji.nakagaki
PR2
17478 Rotate PR2 mirror by IM_YAW picomotor but we had better to use traverser , kouseki.miyo
17520 PR2 Traversor motor and PR2 IM PITCH drive Picomotor , satoru.ikeda
SR2
17434 Cable connection check , naoatsu.hirata
SR3
17439 Cable connection check , naoatsu.hirata
SRM
17314 Optical lever installation , fabian.arellano
This is generated by python script in /users/Miyo/dropbox/Script/scrapping/main.py.
Summary Report
Type-A
- IY: Recovered the F1, F2 FRs. Compressed the F0 blades more to extend the height range. Total adjustable range became +/- 10.6mm.
- IX: Calibrated the BF damper. The LVDT driver was replaced to the low noise one.
- The corrugate tube fixing jigs were replaced in IY, EY, and EX.
Type-B
- This week we installed SR2 oplev hardware and routed the power cable from the rack to the SLED. Next week we'll align the optical components.
- On the week before the ast one, we installed the SRM oplev optics, aligned the optical components and calibrated the QPD in terms of their displacements.
Type-Bp
Type-C
Electronics
Control
Schedule
See Schedule
- Type-A team: Finalization of IX and EX.
- Type-B team: MSB
Milestone
IMC suspensions are ready in air [40] will finish 2021/04/21.
PRs are ready in air [643] will finish 2021/07/09.
ETMX is ready in air [656] will finish 2021/08/25.
ITMX is ready in air [657] will finish 2021/08/31.
ETMY is ready in air [658] will finish 2021/09/16.
ITMY is ready in air [659] will finish 2021/11/08.
BS is ready in air [691] will finish 2021/11/24.
SRs are ready in air [663] will finish 2021/12/20.
Output suspensions are ready in air [695] will finish 2021/12/21.
TMSY is ready in air [708] will finish 2021/??/??.
TMSX is ready in air [684] will finish 2021/??/??.
2021/03/29 updated
Safety
Discussion
BS Outer frame
- The brace (support beam) for BS outer frame was not attached in O3. The brace itself is ready.
- We have a structure analysis for the frame prototype (SR type), but not for the BS type.
- I like to ask Sato-san the analysis for BS type to confirm the availability.
Travel Plans
The week from 7/19
- Takahashi: 7/19-21
- Sato: 7/19-21
- Hirata: 7/19-21
- Yano: 7/19-21
The week from 7/26
- Takahashi: 7/26-30
- Hirata: 7/26-30
- Yano: 7/26-30
Next meeting
- 2021/7/30(FRI)