Line 8: Line 8:
Date: 2021/7/9 13:00-14:00

Participants: Takahashi, Ikeda, Sato, Ushiba, Kimura, Aso, Tomaru, Node, Hirata
Date: 2021/7/16 13:00-13:35

Participants: Takahashi, Node, Ikeda, Ushiba, Tomaru, Sato, Aso, Kimura, Miyo
Line 15: Line 15:
 * IX: To the finalization.
 * EX: Alignment for the green beam was finished. To the finalization
 * IY: Height adjustment is on going.
 * EY: Mirror cleaning is on going in Mitaka. Measurement system had a problem. The shipping will be in the end of next week at earliest.
 * IX: Still some cabling from payload have problems. To the finalization.
 * EX: Aligned for the green beam again. To the finalization
 * IY: F1 was recovered. Adjustable range of F0 was extended ([[https://www.dropbox.com/s/a8p7m6luxz6ndwn/Height%20range%20rev.pdf?dl=0|Height range]]). Range of BF damper should be taken into account. The height adjustment was scheduled in the week of 7/26.
 * EY: Mirror cleaning was almost finished. The shipping will be in the next week (transported after holidays).
Line 21: Line 21:
 * Corrugate tube fixing jig: Implementation is scheduled on 7/12-13.  * Corrugate tube fixing jig: Replaced on 7/12-13.
Line 23: Line 23:
 * Commissioning in air: X-arm.  * Commissioning in air: on going in X-arm. Oplev calibration is necessary.
Line 28: Line 28:
 * Separation of rack in 2F: This is scheduled on 7/16.
 * New vacuum pumps for V-chambers: Considering the port location.
 * Extension of cables
for picomotor drivers: Tested in EYV.
 * Separation of rack in 2F: It was finished on 7/16.
 * New vacuum pumps for V-chambers: Problem on the support for GVs.
Line 33: Line 32:
Adjustable height range of the filter chain in IY
 * [[https://www.dropbox.com/s/i7e0grqv324sdfz/Height%20range.pdf?dl=0|Present height range]]
 * The condition of F1 stepper motor is the same as the F3 in IX. We tried to move the motor with the stand alone driver, but the FR is still not working.
  * The motor is still not working?
  * The FR slider is stuck?
 * The range of BF is too small. Check the mechanical stopper.
 * Tune the F0 more to lower frequency (now 0.4Hz) in order to extend the range.

== Next meeting ==
 * 2021/7/16(FRI)
----------
= VIS Meeting =
14:00-14:20

Participants: Takahashi, Miyo, Terrence, Sato, Fabian, Aso, Tanaka, Ishizaki
Line 46: Line 40:
Line 49: Line 44:
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17267|17267]] Oplev preparation work EX , __takaaki.yokozawa__ 
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17362|17362]] Comment , __takaaki.yokozawa__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17358|17358]] Injection of OpLev lasers to the cryostat at EXC , __takafumi.ushiba__ 
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17361|17361]] Comment , __takaaki.yokozawa__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17496|17496]] ETMX IM photosensor trouble shooting , __takafumi.ushiba__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17503|17503]] Rebooter installation for pico motor drivers. (ETMX) , __koji.nakagaki__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17506|17506]] Replacement of fixing jigs for the corrugate tube , __ryutaro.takahashi__
* [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17267|17267]] Oplev preparation work EX , __takaaki.yokozawa__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17362|17362]] Comment , __takaaki.yokozawa__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17358|17358]] Injection of OpLev lasers to the cryostat at EXC , __takafumi.ushiba__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17361|17361]] Comment , __takaaki.yokozawa__
Line 54: Line 53:
Line 55: Line 55:
  * '''EY'''
 * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17485|17485]] Replacement of fixing jigs for the corrugate tube , __ryutaro.takahashi__
  * '''General'''
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17485|17485]] Replacement of fixing jigs for the corrugate tube , __ryutaro.takahashi__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17485|17485]] Replacement of fixing jigs for the corrugate tube , __ryutaro.takahashi__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17505|17505]] Comment , __ryutaro.takahashi__

'''General'''
Line 59: Line 62:
  * '''General'''
Line 61: Line 63:
  * '''General'''
Line 63: Line 64:
  * '''General'''
Line 65: Line 65:
 *  '''General'''
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17079|17079]] Organizing DAQ channels for VIS , __satoru.ikeda__    * '''General'''
* [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17460|17460]] Comment , __satoru.ikeda__
 *
  *
'''IX'''
 * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17513|17513]] Safe.snap of MCi,e,o are updated after Miyoki-san closed laser shutter. , __kouseki.miyo__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17079|17079]] Organizing DAQ channels for VIS , __satoru.ikeda__
 
* [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17460|17460]] Comment , __satoru.ikeda__

'''IX'''
Line 72: Line 72:
  * '''IX'''
Line 74: Line 73:
  * '''IX'''
Line 76: Line 74:
  * '''IX'''
Line 78: Line 75:
  *  '''IX'''
 * (!)
[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17482|17482]] Re-calibration of the IX TM length oplev , __takaaki.yokozawa__
  *  '''IX'''
 * (!)
[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17481|17481]] ITMX MNH1 cable repairement , __takafumi.ushiba__
 *  '''IX'''
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17335|17335]] Checked resistance of TF and BF LVDT actuators coil. , __naohisa.satou__    * '''IX'''
* [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17367|17367]] Comment , __naohisa.satou__
  *  '''IX'''
 *
[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17377|17377]] Comment , __ryutaro.takahashi__
 * '''IX'''

 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17405|17405]] IX Pico motor driver was broken and replaced. , __koji.nakagaki__    * '''IX'''
* [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17420|17420]] Comment , __satoru.ikeda__
 *  '''IX'''
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17449|17449]] Oplev calibration IX
TM oplevs , __takaaki.yokozawa__ 
  *  '''IX'''
 *
[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17461|17461]] Comment , __takafumi.ushiba__
  * '''IX'''
* [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17469|17469]] Comment , __takafumi.ushiba__
 *  '''IX'''
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17468|17468]] MNH1 actuator of ITMX seems to have an issue. , __takafumi.ushiba__ 
  *  '''IX'''
* [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17472|17472]] Comment , __takafumi.ushiba__
 * '''IX'''

 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=8564|8564]] ITMX healthy check after pump down , __lucia.trozzo__    * '''IX'''
* [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17366|17366]] Comment , __kouseki.miyo__
 *
  *
'''IY'''
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17482|17482]] Re-calibration of the IX TM length oplev ,  __takaaki.yokozawa__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17481|17481]] ITMX MNH1 cable repairement ,  __takafumi.ushiba__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17247|17247]] Rebooter installation for pico motor drivers. (ITMX) , __koji.nakagaki__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17502|17502]] Comment , __koji.nakagaki__
  * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17522|17522]] Comment , __koji.nakagaki__

 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17335|17335]] Checked resistance of TF and BF LVDT actuators coil. , __naohisa.satou__
 
* [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17367|17367]] Comment , __naohisa.satou__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17377|17377]] Comment , __ryutaro.takahashi__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17405|17405]] IX Pico motor driver was broken and replaced. , __koji.nakagaki__
 
* [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17420|17420]] Comment , __satoru.ikeda__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17449|17449]] Oplev calibration IX TM oplevs , __takaaki.yokozawa__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17461|17461]] Comment , __takafumi.ushiba__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17469|17469]] Comment , __takafumi.ushiba__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17497|17497]] Comment , __kouseki.miyo__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17468|17468]] MNH1 actuator of ITMX seems to have an issue. , __takafumi.ushiba__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17472|17472]] Comment , __takafumi.ushiba__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17481|17481]] ITMX MNH1 cable repairement , __takafumi.ushiba__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17501|17501]] Comment , __takafumi.ushiba__
  * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17516|17516]] Comment , __takafumi.ushiba__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17482|17482]] Re-calibration of the
IX TM length oplev , __takaaki.yokozawa__
 
* [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17488|17488]] Comment , __takafumi.ushiba__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=8564|8564]] ITMX healthy check after pump down , __lucia.trozzo__
 
* [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17366|17366]] Comment , __kouseki.miyo__

'''IY'''
Line 109: Line 102:
  * '''IY'''
 * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17484|17484]] Replacement of fixing jigs for the corrugate tube , __ryutaro.takahashi__
 * '''IY'''
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17406|17406]] Setup of pre-isolator , __ryutaro.takahashi__
  * '''IY'''
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17431|17431]] Comment , __ryutaro.takahashi__
  * '''IY'''
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17441|17441]] Comment , __ryutaro.takahashi__
 *
  * '''PR2'''
 * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17478|17478]] Rotate PR2 mirror by IM_YAW picomotor but we had better to use traverser , __kouseki.miyo__
  * '''SR2'''
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17484|17484]] Replacement of fixing jigs for the corrugate tube , __ryutaro.takahashi__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17406|17406]] Setup of pre-isolator , __ryutaro.takahashi__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17431|17431]] Comment , __ryutaro.takahashi__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17441|17441]] Comment , __ryutaro.takahashi__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17498|17498]] Comment , __naohisa.satou__
  * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17526|17526]] Comment , __ryutaro.takahashi__

'''MCE'''

 * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17523|17523]] About the placement of the mini-rack in MCE , __koji.nakagaki__

'''PR2'''

 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17478|17478]] Rotate PR2 mirror by IM_YAW picomotor but we had better to use traverser , __kouseki.miyo__
 * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17520|17520]] PR2 Traversor motor and PR2 IM PITCH drive Picomotor , __satoru.ikeda__

'''SR2'''
Line 122: Line 121:
  * '''SR3'''
'''SR3'''
Line 124: Line 125:
 * '''SRM'''
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17314|17314]] Optical lever installation , __fabian.arellano__    * '''SRM'''
* [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17372|17372]] Comment , __fabian.arellano__

'''SRM'''

* [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17314|17314]] Optical lever installation , __fabian.arellano__
 
* [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17372|17372]] Comment , __fabian.arellano__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=17499|17499]] Comment , __terrence.tsang__
Line 133: Line 136:
 * Adjusted the ballasts on the cryo-payload and the BF in IY. Additional spring was implemented on the BF.
 * Repaired the broken cables for TF/BF actuator opening the chamber. The BF and TF were recovered and the chamber was closed.
 * IY: Recovered the F1, F2 FRs. Compressed the F0 blades more to extend the height range. Total adjustable range became +/- 10.6mm.
 * IX: Calibrated the BF damper. The LVDT driver was replaced to the low noise one.
 * The corrugate tube fixing jigs were replaced in IY, EY, and EX.
Line 137: Line 141:
 * This week we installed SR2 oplev hardware and routed the power cable from the rack to the SLED. Next week we'll align the optical components.
 * On the week before the ast one, we installed the SRM oplev optics, aligned the optical components and calibrated the QPD in terms of their displacements.
 * [Terrence] SRM optical lever was calibrated and diagonalized. But the noise floor is too high to render it useful for my purpose. [[https://klog.icrr.u-tokyo.ac.jp/osl/?r=17499|klog 17499]].
 * I synthesized a sensor correction filter according to the seismometer noise and seismic noise in KAGRA. It resembles the LIGO filter but with lower noise amplification. (show notebook)
 * About SRM.
   * I was given a month to work on the SRM and unfortunately I can't finish everything that I wish to do. Today is the deadline so I will stop working on it, unless I am given more time to work on it.
   * It would be useless if I don't share my knowledge with commissioners. But I know you are all busy and you might already have your own plan on how to configure the suspensions. I don't want to force people to listen to my stuff. But, just in case if people want to know how I do particular things, I will be very happy to share.
Line 140: Line 152:
 * Power supply for IX and IY was changed.
Line 144: Line 158:
 * Type-A team: Adjustment of IYV
 * Type-B team: MSB
 * Type-A team: Finalization of IX and EX.
 * Type-B team: Oplev alignment in SR2 and SRM.
Line 165: Line 179:
BS Outer frame

 * The brace (support beam) for BS outer frame was not attached in O3. The brace itself is ready.
 * We have a structure analysis for the frame prototype (SR type), but not for the BS type.
 * I like to ask Sato-san the analysis for BS type to confirm the availability.
Line 166: Line 186:
The week from 7/5

 * Takahashi: 7/5-8 (KIW8 7/7-9)
 * Sato: 7/5-8
 * Hirata: 7/5-9
 * Yano: 7/5-9

The week from 7/12

 * Takahashi: 7/12-16
 * Sato: 7/12-16
 * Hirata: 7/12-16
 * Yano: 7/12-16
The week from 7/19

 * Takahashi: 7/19-21
 * Sato: 7/19-21
 * Hirata: 7/19-21
 * Yano: 7/19-21

The week from 7/26

 * Takahashi: 7/26-30
 * Hirata: 7/26-30
 * Yano: 7/26-30
Line 181: Line 200:
 * 2021/7/16(FRI)  * 2021/7/30(FRI)

Agenda/Minutes

Zoom Meeting


CRY+VIS Interface Meeting

Date: 2021/7/16 13:00-13:35

Participants: Takahashi, Node, Ikeda, Ushiba, Tomaru, Sato, Aso, Kimura, Miyo

Post O3 Upgrade portal

Schedule

  • IX: Still some cabling from payload have problems. To the finalization.
  • EX: Aligned for the green beam again. To the finalization
  • IY: F1 was recovered. Adjustable range of F0 was extended (Height range). Range of BF damper should be taken into account. The height adjustment was scheduled in the week of 7/26.

  • EY: Mirror cleaning was almost finished. The shipping will be in the next week (transported after holidays).

Status

  • Corrugate tube fixing jig: Replaced on 7/12-13.
  • TM height setting: ITMY.
  • Commissioning in air: on going in X-arm. Oplev calibration is necessary.
  • Commissioning in vacuum:
  • Overall commissioning:
  • Acceptance check: Every Friday.
  • PF actuator: After SC.
  • Separation of rack in 2F: It was finished on 7/16.
  • New vacuum pumps for V-chambers: Problem on the support for GVs.

Discussion


VIS Meeting

14:00-14:20

Participants: Takahashi, Miyo, Terrence, Sato, Fabian, Aso, Tanaka, Ishizaki

Klog

EX

  • 17376 ETMX IM dewhitening filters and comb60 filters are implemented , takafumi.ushiba

  • 17396 Oplev preparation at EXC , takaaki.yokozawa

  • 17450 Oplev calibration EX TM oplev , takaaki.yokozawa

  • 17496 ETMX IM photosensor trouble shooting , takafumi.ushiba

  • 17503 Rebooter installation for pico motor drivers. (ETMX) , koji.nakagaki

  • 17506 Replacement of fixing jigs for the corrugate tube , ryutaro.takahashi

  • 17267 Oplev preparation work EX , takaaki.yokozawa

    • 17362 Comment , takaaki.yokozawa

  • 17358 Injection of OpLev lasers to the cryostat at EXC , takafumi.ushiba

    • 17361 Comment , takaaki.yokozawa

EY

  • 17457 dial gauge installation, Pico motor cable extension test , naohisa.satou

  • 17485 Replacement of fixing jigs for the corrugate tube , ryutaro.takahashi

  • 17485 Replacement of fixing jigs for the corrugate tube , ryutaro.takahashi

    • 17505 Comment , ryutaro.takahashi

General

  • 17369 Added EPICS channel for VIS temperature adjustment , satoru.ikeda

  • 17368 Implemented some Oplev-related fixes to the VIS model file. , satoru.ikeda

  • 17388 Implementation of sensor to EULER matrix for IM photosensors , takafumi.ushiba

  • 17455 TypeA,B,Bp VIS Guardian changed to SAFE , satoru.ikeda

  • (!) 17513 Safe.snap of MCi,e,o are updated after Miyoki-san closed laser shutter. , kouseki.miyo

  • 17079 Organizing DAQ channels for VIS , satoru.ikeda

    • 17460 Comment , satoru.ikeda

IX

  • 17400 Modification of damp_temp filter for MN DAMP filter of ITMX , takafumi.ushiba

  • 17405 IX Pico motor driver was broken and replaced. , koji.nakagaki

  • 17449 Oplev calibration IX TM oplevs , takaaki.yokozawa

  • 17468 MNH1 actuator of ITMX seems to have an issue. , takafumi.ushiba

  • 17482 Re-calibration of the IX TM length oplev , takaaki.yokozawa

  • 17481 ITMX MNH1 cable repairement , takafumi.ushiba

  • 17247 Rebooter installation for pico motor drivers. (ITMX) , koji.nakagaki

    • 17502 Comment , koji.nakagaki

    • (!) 17522 Comment , koji.nakagaki

  • 17335 Checked resistance of TF and BF LVDT actuators coil. , naohisa.satou

    • 17367 Comment , naohisa.satou

    • 17377 Comment , ryutaro.takahashi

  • 17405 IX Pico motor driver was broken and replaced. , koji.nakagaki

    • 17420 Comment , satoru.ikeda

  • 17449 Oplev calibration IX TM oplevs , takaaki.yokozawa

    • 17461 Comment , takafumi.ushiba

    • 17469 Comment , takafumi.ushiba

    • 17497 Comment , kouseki.miyo

  • 17468 MNH1 actuator of ITMX seems to have an issue. , takafumi.ushiba

    • 17472 Comment , takafumi.ushiba

  • 17481 ITMX MNH1 cable repairement , takafumi.ushiba

    • 17501 Comment , takafumi.ushiba

    • (!) 17516 Comment , takafumi.ushiba

  • 17482 Re-calibration of the IX TM length oplev , takaaki.yokozawa

    • 17488 Comment , takafumi.ushiba

  • 8564 ITMX healthy check after pump down , lucia.trozzo

    • 17366 Comment , kouseki.miyo

IY

  • 17406 Setup of pre-isolator , ryutaro.takahashi

  • 17484 Replacement of fixing jigs for the corrugate tube , ryutaro.takahashi

  • 17406 Setup of pre-isolator , ryutaro.takahashi

    • 17431 Comment , ryutaro.takahashi

    • 17441 Comment , ryutaro.takahashi

    • 17498 Comment , naohisa.satou

    • (!) 17526 Comment , ryutaro.takahashi

MCE

  • (!) 17523 About the placement of the mini-rack in MCE , koji.nakagaki

PR2

  • 17478 Rotate PR2 mirror by IM_YAW picomotor but we had better to use traverser , kouseki.miyo

  • (!) 17520 PR2 Traversor motor and PR2 IM PITCH drive Picomotor , satoru.ikeda

SR2

  • 17434 Cable connection check , naoatsu.hirata

SR3

  • 17439 Cable connection check , naoatsu.hirata

SRM

  • 17314 Optical lever installation , fabian.arellano

    • 17372 Comment , fabian.arellano

    • 17499 Comment , terrence.tsang

This is generated by python script in /users/Miyo/dropbox/Script/scrapping/main.py.

Summary Report

Type-A

  • IY: Recovered the F1, F2 FRs. Compressed the F0 blades more to extend the height range. Total adjustable range became +/- 10.6mm.
  • IX: Calibrated the BF damper. The LVDT driver was replaced to the low noise one.
  • The corrugate tube fixing jigs were replaced in IY, EY, and EX.

Type-B

  • This week we installed SR2 oplev hardware and routed the power cable from the rack to the SLED. Next week we'll align the optical components.
  • On the week before the ast one, we installed the SRM oplev optics, aligned the optical components and calibrated the QPD in terms of their displacements.
  • [Terrence] SRM optical lever was calibrated and diagonalized. But the noise floor is too high to render it useful for my purpose. klog 17499.

  • I synthesized a sensor correction filter according to the seismometer noise and seismic noise in KAGRA. It resembles the LIGO filter but with lower noise amplification. (show notebook)
  • About SRM.
    • I was given a month to work on the SRM and unfortunately I can't finish everything that I wish to do. Today is the deadline so I will stop working on it, unless I am given more time to work on it.
    • It would be useless if I don't share my knowledge with commissioners. But I know you are all busy and you might already have your own plan on how to configure the suspensions. I don't want to force people to listen to my stuff. But, just in case if people want to know how I do particular things, I will be very happy to share.

Type-Bp

Type-C

Electronics

  • Power supply for IX and IY was changed.

Control

Schedule

See Schedule

  • Type-A team: Finalization of IX and EX.
  • Type-B team: Oplev alignment in SR2 and SRM.

Milestone

  • IMC suspensions are ready in air [40] will finish 2021/04/21.

  • PRs are ready in air [643] will finish 2021/07/09.

  • ETMX is ready in air [656] will finish 2021/08/25.

  • ITMX is ready in air [657] will finish 2021/08/31.

  • ETMY is ready in air [658] will finish 2021/09/16.

  • ITMY is ready in air [659] will finish 2021/11/08.

  • BS is ready in air [691] will finish 2021/11/24.

  • SRs are ready in air [663] will finish 2021/12/20.

  • Output suspensions are ready in air [695] will finish 2021/12/21.

  • TMSY is ready in air [708] will finish 2021/??/??.

  • TMSX is ready in air [684] will finish 2021/??/??.

2021/03/29 updated

Safety

Discussion

BS Outer frame

  • The brace (support beam) for BS outer frame was not attached in O3. The brace itself is ready.
  • We have a structure analysis for the frame prototype (SR type), but not for the BS type.
  • I like to ask Sato-san the analysis for BS type to confirm the availability.

Travel Plans

The week from 7/19

  • Takahashi: 7/19-21
  • Sato: 7/19-21
  • Hirata: 7/19-21
  • Yano: 7/19-21

The week from 7/26

  • Takahashi: 7/26-30
  • Hirata: 7/26-30
  • Yano: 7/26-30

Next meeting

  • 2021/7/30(FRI)

KAGRA/Subgroups/VIS/VISMinutes20210716 (last edited 2021-07-16 14:26:07 by RyutaroTakahashi)