* External review: improvement in the payload and tower, strategy of height adjustment ([[https://www.dropbox.com/s/dsxiw4qf7yzvm3j/Height%20range%20rev2_0001.pdf?dl=0|Height range]]), SC plan | * External review (8/19): improvement in the payload and tower, strategy of height adjustment ([[https://www.dropbox.com/s/dsxiw4qf7yzvm3j/Height%20range%20rev2_0001.pdf?dl=0|Height range]]), SC plan |
Contents
Agenda/Minutes
CRY+VIS Interface Meeting
Date: 2021/8/6 13:00-
Participants:
Schedule
- IX: In finalization. Problem on the cables for payload. Problem of the F2 FR. Installation of the ACCs is scheduled on 8/16-17.
- EX: In finalization. Cable (P7-3) was recovered.
- IY: Height adjustment will be scheduled after vacation.
- EY: Preparation for the payload with the mirror is on going. Installation into the cryostat is scheduled on 8/20.
Status
- TM height setting: ITMY.
- Commissioning in air: on going in X-arm. Oplev calibration.
- Commissioning in vacuum:
- Overall commissioning:
- Acceptance check: Every Friday.
- PF actuator: At the in-vacuum commissioning.
- New vacuum pumps for V-chambers:
Discussion
External review (8/19): improvement in the payload and tower, strategy of height adjustment (Height range), SC plan
VIS Meeting
14:00-
Participants:
Klog
This is generated by python script in /users/Miyo/dropbox/Script/scrapping/main.py.
Summary Report
Type-A
- Repaired the cable for payload in EX.
- Adjusted the height of GAS filters to the setpoints. The FR for F2 in IX didn't work.
- Prepared for the accelerometers.
Type-B
Type-Bp
Type-C
Electronics
Control
Schedule
See Schedule
- Type-A team:
- Type-B team: MSB
Milestone
IMC suspensions are ready in air [40] will finish 2021/04/21.
PRs are ready in air [643] will finish 2021/07/09.
ETMX is ready in air [656] will finish 2021/08/25.
ITMX is ready in air [657] will finish 2021/08/31.
ETMY is ready in air [658] will finish 2021/09/16.
ITMY is ready in air [659] will finish 2021/11/08.
BS is ready in air [691] will finish 2021/11/24.
SRs are ready in air [663] will finish 2021/12/20.
Output suspensions are ready in air [695] will finish 2021/12/21.
TMSY is ready in air [708] will finish 2021/??/??.
TMSX is ready in air [684] will finish 2021/??/??.
2021/03/29 updated
Safety
Discussion
Travel Plans
The week from 8/9
- Hirata: 8/9-13
- Yano: 8/9-13
The week from 8/16
- Takahashi: 8/16-20
- Sato: 8/16-20
Next meeting