<> = Agenda/Minutes = [[https://zoom.us/j/203743987|Zoom Meeting]] ---------- = CRY+VIS Interface Meeting = Date: 2021/8/27 12:30- Participants: Takahashi, Tomaru, Ikeda, Aso, Hirata, Sato, Ushiba [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Upgrades/PostO3Upgrades|Post O3 Upgrade portal]] == Schedule == * IX: In finalization. * EX: In finalization. Installation of ACCs will be scheduled in the next-next week. * IY: Height measurement/adjustment was scheduled on 9/1. * EY: Repair of cables was scheduled on 8/31. Load adjustment was scheduled on 9/2. Chamber closing is scheduled on 9/6-8. == Status == * TM height setting: ITMY. * Commissioning in air: On going in X-arm. * Commissioning in vacuum: * Overall commissioning: * Acceptance check: Every Friday. * PF actuator: At the in-vacuum commissioning. * New vacuum pumps for V-chambers: == Discussion == ---------- = VIS Meeting = == Cancel == Participants: == Klog == This is generated by python script in /users/Miyo/dropbox/Script/scrapping/main.py. == Summary Report == === Type-A === === Type-B === === Type-Bp === === Type-C === === Electronics === === Control === == Schedule == See [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/VIS/Schedule|Schedule]] * Type-A team: * Type-B team: '''Milestone''' * ''IMC suspensions are ready in air [40]'' will finish 2021/04/21. * ''PRs are ready in air [643]'' will finish 2021/07/09. * ''ETMX is ready in air [656]'' will finish 2021/08/25. * ''ITMX is ready in air [657]'' will finish 2021/08/31. * ''ETMY is ready in air [658]'' will finish 2021/09/16. * ''ITMY is ready in air [659]'' will finish 2021/11/08. * ''BS is ready in air [691]'' will finish 2021/11/24. * ''SRs are ready in air [663]'' will finish 2021/12/20. * ''Output suspensions are ready in air [695]'' will finish 2021/12/21. * ''TMSY is ready in air [708]'' will finish 2021/??/??. * ''TMSX is ready in air [684]'' will finish 2021/??/??. 2021/03/29 updated == Safety == == Discussion == == Travel Plans == The week from 8/30 * Takahashi: 8/31-9/3 * Sato: 8/30-9/3 * Hirata: 8/30-9/3 The week from 9/6 == Next meeting == * 2021/9/3(FRI)