Agenda/Minutes
CRY+VIS Interface Meeting
Date: 2021/11/26 13:00-
Participants:
Schedule
- IX: Finalization of cryo-payload.
- EX: Finalization of cryo-payload. Installation of ACCs. Replacement of flip cables.
- IY:
- EY:
Status
- Replacement of Flip cable: EX on 11/25-26. IX in the next week.
- TM height setting: ITMY.
- Oplev: Setup of the TM Oplev in IY after the TM alignment.
- ACC: Installed to EX on 11/24-25. Assembly for EY is ongoing.
- Commissioning in air: GRY.
- Commissioning in vacuum: Chamber closing is scheduled from 12/13.
- Overall commissioning:
- Acceptance check:
- PF actuator: At the in-vacuum commissioning.
- New vacuum pumps for V-chambers: 11/24 in IXV.
- Heater control:
- Power source for Oplev: The next target is IX.
Discussion
VIS Meeting
Date: 2021/11/26 14:00-
Participants:
Summary Report
Type-A
Type-B
Type-Bp
Type-C
Electronics
Control
Schedule
See Schedule
- Type-A team: Finalization of IX and EX.
- Type-B team:
Safety
Discussion
Travel Plans
(Date in Kamioka)
The week from 11/29
- Takahashi: 11/30-12/3
- Sato: 11/30-12/3
- Hirata: 11/30-12/3
The week from 12/6
- Takahashi: 12/7-10
- Sato: 12/7-9
- Hirata: 12/7-10
Next meeting
- 2021/12/3(FRI)