Participants: == Summary Report == === Type-A === === Type-B === === Type-Bp === === Type-C === === Electronics === === Control === == Schedule == See [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/VIS/Schedule|Schedule]] * Type-A team: ACC in EY, Heter test in IXV/EXV * Type-B team: == Safety == == Discussion == == Travel Plans == (Date in Kamioka) The week from 12/27 (Holidays in 12/29-1/3) The week from 1/4 * Takahashi: 1/5-7 * Sato: 1/5-7 * Hirata: 1/5-7 == Next meeting == * 2022/1/7(FRI) |
Contents
Agenda/Minutes
CRY+VIS Interface Meeting
Date: 2021/12/24 13:00-
Participants:
Schedule
- IX: Pump down on 12/23. Glich in the F3 signals.
- EX: In vacuum.
- IY:
- EY: Recovery of the BF problem.
Status
- Replacement of flip cables:
- TM height setting: ITMY.
- Oplev: Setup of the TM Oplev in IY after the TM alignment.
- ACC: Assembly for EY is under way.
- Commissioning in air: Return of GRY.
- Commissioning in vacuum: Pump down of IXC/IXV on 12/23.
- Overall commissioning:
- Acceptance check:
- PF actuator: At the in-vacuum commissioning.
- New vacuum pumps for V-chambers:
- Heater control:
- Power source for Oplev:
Discussion
VIS Meeting
Date: 2021/12/24 14:00-
Participants:
Summary Report
Type-A
Type-B
Type-Bp
Type-C
Electronics
Control
Schedule
See Schedule
- Type-A team: ACC in EY, Heter test in IXV/EXV
- Type-B team:
Safety
Discussion
Travel Plans
(Date in Kamioka)
The week from 12/27
(Holidays in 12/29-1/3)
The week from 1/4
- Takahashi: 1/5-7
- Sato: 1/5-7
- Hirata: 1/5-7
Next meeting
- 2022/1/7(FRI)