Date: 2023/1/6 13:00- | Date: 2023/1/6 13:00-13:20 |
Line 10: | Line 10: |
Participants: | Participants: Takahashi, Uchiyama, Sato, Miyoki, Node, Ushiba, Ikeda, Aso, Akutsu, Hirata, Mitsuhashi |
Line 16: | Line 16: |
* Type-B: Oplev centering and covering in SR3. | * Type-B: Oplev centering and covering in SR3, necessary for also SR2. |
Line 38: | Line 38: |
* Adjusted the heater control in IY. The drift of F0 is large due to the air conditioning in EX. |
Contents
Agenda/Minutes
CRY+VIS Interface Meeting
Date: 2023/1/6 13:00-13:20
Participants: Takahashi, Uchiyama, Sato, Miyoki, Node, Ushiba, Ikeda, Aso, Akutsu, Hirata, Mitsuhashi
Status
- Type-A: Heater control in IY.
- Type-B: Oplev centering and covering in SR3, necessary for also SR2.
- Type-Bp:
- Type-C:
Other items
- Oplev: SR3
- ACC: Evaluation in IX/IY.
- Commissioning:
- Vacuum system:
- Heater control: Adjustment in IY
- TMS:
Discussion
VIS Meeting
Date: 2023/1/6 13:30-
Participants:
Summary Report
Type-A
- Adjusted the heater control in IY. The drift of F0 is large due to the air conditioning in EX.
Type-B
Type-Bp
Type-C
Electronics
Control
Schedule
- Type-A: Investigation of ACCs.
- Type-B/Bp: Vertical sensor correction.
- Type-C:
Safety
Discussion
Travel Plans
(Date in Kamioka)
The week from 1/9
- Takahashi: 1/11-13
- Hirata: 1/12-13
- Mitsuhashi: 1/11-13
Next meeting