Contents
Agenda/Minutes
CRY+VIS Interface Meeting
Date: 2022/1/7 13:00-
Participants:
Schedule
- IX: Investigating the glich in the F3 signals. Go to the health check.
- EX: Go to the health check.
- IY:
- EY: Implementing the damping controls. Repair of F0 actuator. Preparation for ACCs.
Status
- Replacement of flip cables: SR2
- TM height setting: ITMY.
- Oplev: Setup of the TM Oplev in IY after the TM alignment.
- ACC: Experiments in IX/EX. Preparation for EY.
- Commissioning in air: Return of GRY.
- Commissioning in vacuum:
- Overall commissioning:
- Acceptance check:
- PF actuator: At the in-vacuum commissioning.
- New vacuum pumps for V-chambers:
- Heater control: IXV/EXV
- Power source for Oplev:
Discussion
VIS Meeting
Date: 2022/1/7 14:00-
Participants:
Summary Report
Type-A
Type-B
Type-Bp
Type-C
Electronics
Control
Schedule
See Schedule
- Type-A team: ACC in EY, Heter test in IXV/EXV
- Type-B team:
Safety
- The zipper to open/close the roof of the clean booth has been broken in EY. The hook of the crane caught the zipper when the crane was working.
Discussion
Travel Plans
(Date in Kamioka)
The week from 1/11
- Takahashi: 1/12-14
- Sato: 1/12-14
- Hirata: 1/12-14
The week from 1/17
- Takahashi: 1/17-21
- Sato: 1/17-21
- Hirata: 1/17-21
Next meeting
- 2022/1/14(FRI)