Contents
Agenda/Minutes
CRY+VIS Interface Meeting
Date: 2022/1/21 13:00-
Participants:
Schedule
- IX: Health check. Glitch in the F3 signals. Windshield for the MN oplev.
- EX: Health check.
- IY: Installation of the accelerometers.
EY: Repair of the IP H2 actuator. Photosensor V3. LT->Yaw coupling. Preparation for the accelerometers.
Status
- Replacement of flip cables: SRM was finished. Cables for Type-C will be delivered in the end of Jan.
- TM height setting: ETMY, ITMY.
- Oplev: Setup of the TM Oplev in IY after the TM alignment.
- ACC: Preparation for EY.
- Commissioning in air: Return of GRY. Alignment of SR3/ETMY.
- Commissioning in vacuum: Go to the stable lock.
- Overall commissioning:
- Acceptance check:
- PF actuator: At the in-vacuum commissioning.
- New vacuum pumps for V-chambers:
- Heater control: Test in IXV/EXV is planed. Repaired power controller was delivered.
- Power source for Oplev:
- Tunnel for the IYC booth: Planed on 1/31.
Discussion
VIS Meeting
Date: 2022/1/21 14:00-
Participants:
Summary Report
Type-A
Type-B
Type-Bp
Type-C
Electronics
Control
Schedule
See Schedule
- Type-A team: Installation of the accelerometers in EY, Height adjustment of ETMY.
- Type-B team:
Safety
Discussion
Travel Plans
(Date in Kamioka)
The week from 1/24
- Takahashi: 1/25-28
- Sato: 1/25-28
- Hirata: 1/25-28
The week from 1/31
- Takahashi: 1/31-2/4
- Sato: 1/31-2/4
- Hirata: 1/31-2/4
Next meeting
- 2022/1/28(FRI)