Differences between revisions 6 and 7
Revision 6 as of 2022-02-04 13:55:00
Size: 3715
Comment:
Revision 7 as of 2022-02-04 13:58:46
Size: 3713
Comment:
Deletions are marked like this. Additions are marked like this.
Line 50: Line 50:
* BS F1 LVDT:  * BS F1 LVDT:
Line 52: Line 52:
  * In order to solve this, I modified the LVDT calibration offset to yield zero, when the keystone is at the nominal 3D-CAD position. I achieved this using the old and new calibration data.
   * The difference between the setpoints is only 324 um, which is negligible in terms of the uncertainties we have when we measure the height of the optic.
  * The amount of actuation reduced to around -8,000 counts, and will decrease more when the system goes into vacuum.
  * In order to solve this, I modified the LVDT calibration offset to yield zero, when the keystone is at the nominal 3D-CAD position. I achieved this using the old and new calibration data.
  * The difference between the setpoints is only 324 um, which is negligible in terms of the uncertainties we have when we measure the height of the optic.
  * The amount of actuation reduced to around -8,000 counts, and will decrease more when the system goes into vacuum.

Agenda/Minutes

Zoom Meeting


CRY+VIS Interface Meeting

Date: 2022/2/4 13:00-13:35

Participants: Takahashi, Uchiyama, Node, Hirata, Yasui, Sato, Tomaru, Yokozawa, Ikeda, Kimura, Suzuki, Aso, Ushiba

Post O3 Upgrade portal

Schedule

  • IX: Glitch in the F3 signals. Windshield for the MN oplev.
  • EX: Health check will be done after the vacuum issue. Repair of the feedthrough is scheduled on 2/9-10.
  • IY: Height adjustment was done on 2/1.
  • EY: Height measurement was done on 2/1. Oplev setting in Feb. Preparation for the accelerometers.

Status

  • Replacement of flip cables: Type-C. Cables were delivered.
  • TM height setting: Measurement for ITMY.
  • Oplev: Setup of the TM Oplev in IY after the TM alignment in late Feb.
  • ACC: Preparation for EY.
  • Commissioning in air: Return of GRY. Fluctuation of ETMY is large. MN oplev control is necessary.
  • Commissioning in vacuum:
  • Overall commissioning:
  • Acceptance check:
  • PF actuator: At the in-vacuum commissioning.
  • New vacuum pumps for V-chambers: EXV (transportation on 2/7, implementation on 2/8-11)
  • Heater control: Test in IXV/EXV.
  • Power source for Oplev: IY.
  • TMS: Scheduled on 2/14-16.

Discussion


VIS Meeting

Date: 2022/2/4 14:00-

Participants:

Summary Report

Type-A

  • Adjusted the height of ITMY and F1 damper.
  • Investigating the noise source in the accelerometers.
  • Repaired the F0 yaw FR in EY.

Type-B

  • BS F1 LVDT:
    • After calibration last week, I updated the medm values accordingly, however, the amount of actuation needed to move the keystone to the setpoint was too high (-26,000 counts).
    • In order to solve this, I modified the LVDT calibration offset to yield zero, when the keystone is at the nominal 3D-CAD position. I achieved this using the old and new calibration data.
    • The difference between the setpoints is only 324 um, which is negligible in terms of the uncertainties we have when we measure the height of the optic.
    • The amount of actuation reduced to around -8,000 counts, and will decrease more when the system goes into vacuum.
  • Terrence reported there is some residual motion in the BS suspension. The oplev measures a 50 mHz yaw oscillation, which the damper ring is supposed to damp.
    • I assessed the performance of the damper ring with the F0 keystone at two different heights, and from visual inspection of the time series, it seems to be working.
    • The residual motion is even there with the control system off.
    • Currently, we have the impression it might be an environmental influence. The chamber is not properly shielded against air currents.
    • We need to repeat some measurements when there is no one working in the tunnel, and if this does not produce good results, we would like to close the chamber with the clean clothes rather than with the improvised aluminium duct.

Type-Bp

We inspected PR2 traverser, checked a cable and adjusted the height of PR3 suspended breadboard.

Type-C

Electronics

Control

Schedule

See Schedule

  • Type-A team: Accelerometers in IY/EY.
  • Type-B team:

Safety

Discussion

Travel Plans

(Date in Kamioka)

The week from 2/7

  • Takahashi: 2/8-10
  • Sato: 2/8-10
  • Hirata: 2/8-10

The week from 2/14

  • Takahashi: 2/15-18
  • Sato: 2/15-18
  • Hirata: 2/15-18

Next meeting

  • 2022/2/18(FRI)

KAGRA/Subgroups/VIS/VISMinutes20220204 (last edited 2022-02-04 15:04:44 by RyutaroTakahashi)