Line 8: Line 8:
Date: 2022/3/4 13:00- Date: 2022/3/4 13:00-13:30
Line 10: Line 10:
Participants: Participants: Takahashi, Akutsu, Ikeda, Ushiba, Aso, Node, Sato, Miyoki, Hirata
Line 15: Line 15:
 * IX: Glitch in the F3 signals. Windshield for the MN oplev. Cooling of the cryo-shield.  * IX: Glitch in the Oplev signal was reduced in the circuit. 
Line 18: Line 18:
 * EY: Preparation for the accelerometers.  * EY: Preparation for the accelerometers. The pump was set on 3/4.
Line 23: Line 23:
 * Oplev: Setup of the Oplev in EY was in 70%. Not yet in IY.  * Oplev: Setup of the Oplev in EY was almost done. Not yet in IY.
Line 26: Line 26:
 * Commissioning in vacuum:  * Commissioning in vacuum: Lock time is about 30min.
Line 32: Line 32:
 * Power source for Oplev: Check of the electric ports is scheduled on 3/15.  * Power source for Oplev: Check of the electric ports in 3/2-3.
Line 38: Line 38:
Date: 2022/2/25 14:00- Date: 2022/3/4 14:00-

Agenda/Minutes

Zoom Meeting


CRY+VIS Interface Meeting

Date: 2022/3/4 13:00-13:30

Participants: Takahashi, Akutsu, Ikeda, Ushiba, Aso, Node, Sato, Miyoki, Hirata

Post O3 Upgrade portal

Schedule

  • IX: Glitch in the Oplev signal was reduced in the circuit.
  • EX: Health check.
  • IY: Investigation of the suspension behavior.
  • EY: Preparation for the accelerometers. The pump was set on 3/4.

Status

  • Replacement of flip cables: Stock of the feedthrough flange.
  • TM height setting: ITMY.
  • Oplev: Setup of the Oplev in EY was almost done. Not yet in IY.
  • ACC: Installation was postponed in EY.
  • Commissioning in air: Alignment of ITMY.
  • Commissioning in vacuum: Lock time is about 30min.
  • Overall commissioning:
  • Acceptance check:
  • PF actuator: At the in-vacuum commissioning.
  • New vacuum pumps for V-chambers: Implementation in this week.
  • Heater control: Test in IXV/EXV.
  • Power source for Oplev: Check of the electric ports in 3/2-3.
  • TMS: Installation of the balancer in 2/28-3/1.

Discussion


VIS Meeting

Date: 2022/3/4 14:00-

Participants:

Summary Report

Type-A

  • Investigating the suspension behavior in IY.

[Ishizaki]

  • Bending test of the SiC pipe (Report).

Type-B

Type-Bp

Type-C

Electronics

Control

Schedule

See Schedule

  • Type-A team: Investigation of GAS filters in IY. Installation of ACCs in EY.
  • Type-B team:

Safety

Discussion

Travel Plans

(Date in Kamioka)

The week from 3/7

  • Takahashi: 3/7-11
  • Sato: 3/7-11
  • Hirata: 3/8-11

The week from 3/14

  • Takahashi: 3/15-18
  • Sato: 3/15-18
  • Hirata: 3/15-18

Next meeting

  • 2022/3/11(FRI)