Agenda/Minutes

Zoom Meeting


CRY+VIS Interface Meeting

Date: 2022/4/15 13:00-

Participants:

Post O3 Upgrade portal

Schedule

  • IX: F0 overload
  • EX:
  • IY: Health check. Go to finalization (WAB, Frame adjustment).
  • EY: TM actuator problem (flip cable, regluing of magnet).
  • Type-B/Bp/C: BFH LVDT was recovered in PRM. Leak in IMC.

Status

  • Replacement of flip cables: Cables for TMS were ordered. Feedthrough flange was replaced with the blank flange in OMC.
  • TM height setting: ITMY.
  • Oplev: Calibration in EY. Windshield in the next.
  • ACC:
  • Commissioning in air:
  • Commissioning in vacuum:
  • Acceptance check:
  • PF actuator: At the in-vacuum commissioning.
  • New vacuum pumps for V-chambers:
  • Heater control: Test is pending.
  • TMS: Pressure was increased in EXT.

Discussion


VIS Meeting

Date: 2022/4/15 14:00-

Participants:

Summary Report

Type-A

  • Recovery of the TM actuator in EY.
  • Saturation of the F0 keystone height.

Type-B

Type-Bp

Type-C

Electronics

Control

Schedule

See Schedule

  • Type-A team: Finalization of IY/EY.
  • Type-B team:

Safety

Discussion

Travel Plans

(Date in Kamioka)

The week from 4/18

  • Takahashi: 4/19-22
  • Sato: 4/19-22
  • Hirata: 4/19-22

The week from 4/25

  • Takahashi: 4/25-28
  • Sato: 4/25-28
  • Hirata: 4/25-28

Next meeting

  • 2022/4/22(FRI)