Line 8: Line 8:
Date: 2022/4/22 13:00- Date: 2022/4/22 13:00-13:20
Line 10: Line 10:
Participants: Participants: Takahashi, Ikeda, Sato, Yasui, Uchiyama, Aso, Akutsu, Ushiba, Yokozawa
Line 18: Line 18:
 * EY: MN H1 photosensor. TM actuator. Go to finalization.  * EY: MN H1 photosensor. TM actuator. Cleaning of EYV. Go to finalization.
Line 29: Line 29:
 * Commissioning in vacuum: Alignment of IOO and X-arm.  * Commissioning in vacuum: Alignment of IO and X-arm.
Line 39: Line 39:
Date: 2022/4/22 14:00- Date: 2022/4/22 14:00-14:10
Line 41: Line 41:
Participants: Participants: Takahashi, Fabian, Uchiyama, Tanaka, Ushiba, Aso, Washimi
Line 48: Line 48:
 * Takahashi-san compared SR2 IP TF measurements with those of SRM, and found some discrepancies. The problem was likely produced by the geophone integrator being off. In SR2 it has to be turned on by hand. I measured the same TFs this week and they are fine.
 * With the aim of understanding Terrece's work, in SR2 I tried to do the inter calibration between geophoes and LVDT. At low frequencies the inter calibration seems be good already, but around 1 Hz, where the resonant frequency of the geophone is, there is a deformation of the TF. I've been looking into this, but I don't have anything relevant to report yet.
Line 49: Line 52:
 * Traverser limit SW: Jig (braket), Touch sensor, PLC, In-vac cable.  * As a result of discussion with the ATC, we add the limit switches to also the stages without the stepper motors. There are some items to be ordered; Jigs (bracket), Touch sensors, PLC board, and In-vac cables.

Agenda/Minutes

Zoom Meeting


CRY+VIS Interface Meeting

Date: 2022/4/22 13:00-13:20

Participants: Takahashi, Ikeda, Sato, Yasui, Uchiyama, Aso, Akutsu, Ushiba, Yokozawa

Post O3 Upgrade portal

Schedule

  • IX: F0 overload.
  • EX:
  • IY: Health check. ACC noise. Cleaning of IYV. Go to finalization.
  • EY: MN H1 photosensor. TM actuator. Cleaning of EYV. Go to finalization.
  • Type-B: Health check in SRM. Calibration of geophone in SR2. Stand-alone SM driver for SR3.
  • Type-Bp: Traverser limit SW.
  • Type-C: OFI removal.

Status

  • Replacement of flip cables: Cables for TMS were ordered.
  • TM height setting: ITMY.
  • Oplev: Windshield in the next.
  • ACC: Investigating the noise source.
  • Commissioning in air:
  • Commissioning in vacuum: Alignment of IO and X-arm.
  • Acceptance check:
  • PF actuator: At the in-vacuum commissioning.
  • New vacuum pumps for V-chambers:
  • Heater control: Test is pending.
  • TMS:

Discussion


VIS Meeting

Date: 2022/4/22 14:00-14:10

Participants: Takahashi, Fabian, Uchiyama, Tanaka, Ushiba, Aso, Washimi

Summary Report

Type-A

  • Cleaning of IYV and EYV.

Type-B

  • Takahashi-san compared SR2 IP TF measurements with those of SRM, and found some discrepancies. The problem was likely produced by the geophone integrator being off. In SR2 it has to be turned on by hand. I measured the same TFs this week and they are fine.
  • With the aim of understanding Terrece's work, in SR2 I tried to do the inter calibration between geophoes and LVDT. At low frequencies the inter calibration seems be good already, but around 1 Hz, where the resonant frequency of the geophone is, there is a deformation of the TF. I've been looking into this, but I don't have anything relevant to report yet.

Type-Bp

  • As a result of discussion with the ATC, we add the limit switches to also the stages without the stepper motors. There are some items to be ordered; Jigs (bracket), Touch sensors, PLC board, and In-vac cables.

Type-C

Electronics

Control

Schedule

See Schedule

  • Type-A team: Finalization in IY/EY.
  • Type-B team:

Safety

Discussion

Travel Plans

(Date in Kamioka)

The week from 4/25

  • Takahashi: 4/25-28
  • Sato: 4/25-28
  • Hirata: 4/25-28

The week from 5/2

Next meeting

  • 2022/5/6(FRI)