998
Comment:
|
1188
|
Deletions are marked like this. | Additions are marked like this. |
Line 21: | Line 21: |
* Disassembled the footholds around the top chamber in EY. |
|
Line 23: | Line 25: |
* Measured the transfer functions of the PR suspensions. |
|
Line 24: | Line 28: |
* Installed the repaired high power coil driver to the OMMT1. |
Contents
Agenda/Minutes
CRY+VIS Interface Meeting
Date: 2022/5/20 13:00-
Review of IY and EY
VIS Meeting
Date: 2022/5/20 14:00-
Participants:
Summary Report
Type-A
- Disassembled the footholds around the top chamber in EY.
Type-B
Type-Bp
- Measured the transfer functions of the PR suspensions.
Type-C
- Installed the repaired high power coil driver to the OMMT1.
Electronics
Control
Schedule
See Schedule
- Type-A: Monitoring of the evacuation in IY/EY.
- Type-B/Bp/C:
Safety
Discussion
Travel Plans
(Date in Kamioka)
The week from 5/23
- Takahashi: 5/23-26
- Sato: 5/23-27
- Hirata: 5/23-27
- Aso: 5/23-26
The week from 5/30
- Takahashi: 5/30-6/3
- Sato: 5/30-6/3
- Hirata: 5/30-6/3
Next meeting
- 2022/5/27(FRI)