Date: 2022/6/10 13:00- | Date: 2022/6/10 13:00-13:25 |
Line 10: | Line 10: |
Participants: | Participants: Takahashi, Yokozawa, Uchiyama, Ushiba, Ikeda, Aso, Sato, Miyoki, Akutsu, Kimura, Hirata |
Line 20: | Line 20: |
* Type-Bp: FC on PR3. Installation of traverser limit SW in PR3. For PR2 in the next week. MSB to PR3 in the next week. * Type-C: Alignment of OMC. Recovery of OMMT2 suspension. Adjustment of H3 OSEM in OMMT1 in the next week. |
* Type-Bp: FC on PR3. Installation of traverser limit SW in PR3. For PR2 in 6/14-15. MSB to PR3 in 6/16-17. * Type-C: Alignment of OMC. Recovery of OMMT2 suspension. Adjustment of H3 OSEM in OMMT1 after the final alignment (if possible). |
Line 26: | Line 26: |
* Oplev: | * Oplev: Investigating the relation between laser and temperature. |
Line 29: | Line 29: |
* Commissioning in vacuum: Y-arm lock in IR. | * Commissioning in vacuum: GR in Y-arm. |
Line 32: | Line 32: |
* New vacuum pumps for V-chambers: Test in IYV. | * New vacuum pumps for V-chambers: Fan was attached to IYV pump. Test in the next week. |
Line 39: | Line 39: |
Date: 2022/6/10 14:00- | Date: 2022/6/10 14:00-14:15 |
Line 41: | Line 41: |
Participants: | Participants: Takahashi, Uchiyama, Ushiba, Fabian, Tanaka, Aso |
Line 51: | Line 51: |
* We installed new cable clamps and limit switches in PR3. * We locked the suspension for First Contact application. |
|
Line 53: | Line 56: |
* Performed the health check of OMMT1, OMMT2 and OSTM after the OMC alignment. It is necessary to adjust the H3 OSEM in OMMT1. | * Performed the health check of OMMT1, OMMT2, and OSTM after the OMC alignment. It is necessary to adjust the H3 OSEM in OMMT1. |
Line 60: | Line 63: |
* Type-B: | * Type-B: Stand-alone SM driver for SR3, Geophone work in SR2. |
Line 62: | Line 65: |
* Type-C: H3 OSEM in OMMT1. | * Type-C: |
Contents
Agenda/Minutes
CRY+VIS Interface Meeting
Date: 2022/6/10 13:00-13:25
Participants: Takahashi, Yokozawa, Uchiyama, Ushiba, Ikeda, Aso, Sato, Miyoki, Akutsu, Kimura, Hirata
Schedule
- IX:
- EX: Height adjustment of ETMX. Centering of QPD in TMSX.
- IY: Leak test in the next week.
- EY: Offload of GAS filters.
- Type-B: Replacement of H2 geophone in SR2. Stand-alone SM driver for SR3.
- Type-Bp: FC on PR3. Installation of traverser limit SW in PR3. For PR2 in 6/14-15. MSB to PR3 in 6/16-17.
- Type-C: Alignment of OMC. Recovery of OMMT2 suspension. Adjustment of H3 OSEM in OMMT1 after the final alignment (if possible).
Status
- Replacement of flip cables: EXT and BF temp.
- TM height setting: Following the cooling.
- Oplev: Investigating the relation between laser and temperature.
- ACC:
- Commissioning in air:
- Commissioning in vacuum: GR in Y-arm.
- Acceptance check:
- PF actuator: At the in-vacuum commissioning.
- New vacuum pumps for V-chambers: Fan was attached to IYV pump. Test in the next week.
- Heater control: Pending.
- TMS: QPD in EX.
Discussion
VIS Meeting
Date: 2022/6/10 14:00-14:15
Participants: Takahashi, Uchiyama, Ushiba, Fabian, Tanaka, Aso
Summary Report
Type-A
- Adjusted the height of ETMX.
- Offloaded the GAS filters in EY and IY.
Type-B
In SR2 we identified that geophone 2 had a problem, so we replaced it with a spare one. Takahashi-san gave me the information about calibration factors, but I still have to take a look at it.
Type-Bp
- We installed new cable clamps and limit switches in PR3.
- We locked the suspension for First Contact application.
Type-C
- Recovered the IM touching the magnets in OMMT2 suspension.
- Performed the health check of OMMT1, OMMT2, and OSTM after the OMC alignment. It is necessary to adjust the H3 OSEM in OMMT1.
Electronics
Control
Schedule
- Type-A:
- Type-B: Stand-alone SM driver for SR3, Geophone work in SR2.
- Type-Bp: MSB on PR3. Traverser limit SW in PR2.
- Type-C:
Safety
Discussion
Travel Plans
(Date in Kamioka)
The week from 6/13
- Takahashi: 6/14-17
- Sato: 6/14-17
- Hirata: 6/14-17
The week from 6/20
- Takahashi:
- Sato:
- Hirata:
Next meeting
- 2022/6/17(FRI)