* Type-Bp: Recovery of the alignmenet after the FC in PR3. Installation of traverser limit SW in PR2. MSB to PR3. Health check in the next week. | * Type-Bp: Recovery of the alignmenet after the FC in PR3. Installation of traverser limit SW in PR2. Installation of the MSB in PR3. Health check in the next week. |
Contents
Agenda/Minutes
CRY+VIS Interface Meeting
Date: 2022/6/17 13:00-
Participants:
Schedule
IX: Heater control of the laser for OpLev.
- EX:
- IY: Leak test. Installation of the Windshield.
- EY: Vent in the next week.
- Type-B: Stand-alone SM driver for SR3.
- Type-Bp: Recovery of the alignmenet after the FC in PR3. Installation of traverser limit SW in PR2. Installation of the MSB in PR3. Health check in the next week.
- Type-C:
Status
- Replacement of flip cables: EXT and BF temp.
- TM height setting: Following the cooling.
- Oplev: Investigating the relation between laser and temperature.
- ACC:
- Commissioning in air:
- Commissioning in vacuum:
- Acceptance check:
- PF actuator: At the in-vacuum commissioning.
- New vacuum pumps for V-chambers: Test of the IYV pump.
- Heater control: Pending.
- TMS:
Discussion
VIS Meeting
Date: 2022/6/17 14:00-
Participants:
Summary Report
Type-A
Type-B
Type-Bp
Type-C
Electronics
Control
Schedule
- Type-A: Monitoring during the vent in EY.
- Type-B: FC to SR3/SRM. Investigation on the mirror replacement in SRM.
- Type-Bp: Test of the traverser limit SW in PR2. Health check.
- Type-C:
Safety
Discussion
Travel Plans
(Date in Kamioka)
The week from 6/20
- Takahashi:
- Sato:
- Hirata: 6/21-24
The week from 6/27
- Takahashi: 6/27-7/1
- Sato: 6/28-7/1
- Hirata: 6/28-7/1
Next meeting
- 2022/6/24(FRI)