Line 18: Line 18:
 * EY: Vent and monitor. Repair of leak in the next week.  * EY: Vent and monitor. Repair of leak and pump-down in the next week. 
Line 21: Line 21:
 * Type-C:  * Type-C: Health check should be scheduled.
Line 26: Line 26:
 * Oplev: Investigating the relation between laser and temperature. Adjustment for PRM.  * Oplev: Investigating the relation between laser and temperature. Adjustment for PRM. For SRs in the next week.
Line 34: Line 34:
 * TMS:  * TMS: Window to EYT in the next week.
Line 39: Line 39:
Date: 2022/6/24 14:00- Date: 2022/6/24 14:00-14:15
Line 41: Line 41:
Participants: Participants: Takahashi, Uchiyama, Ushiba, Fabian, Tanaka, Aso, Washimi
Line 45: Line 45:
 * Monitored the build up. Height of the top chamber was changed by 1mm.
Line 60: Line 62:
 * Type-A:
 * Type-B: MSB in SR3/SRM.
 * Type-A: Monitor of pump down.
 * Type-B: MSB in SR3/SRM. OpLev setting.

Agenda/Minutes

Zoom Meeting


CRY+VIS Interface Meeting

Date: 2022/6/24 13:00-13:50

Participants: Takahashi, Sato, Uchiyama, Yokozawa, Aso, Kimura, Miyoki, Ushiba, Akutsu, Ikeda

Post O3 Upgrade portal

Schedule

  • IX: Heater control of the laser for OpLev.

  • EX:
  • IY: Cooling of the ducts is ready.
  • EY: Vent and monitor. Repair of leak and pump-down in the next week.
  • Type-B: Stand-alone SM driver for SR3. FC to SR3/SRM. Investigation of the mirror replacement in SRM. Installation of the MSB to SR3/SRM in the next week.
  • Type-Bp: Test of the traverser limit SW in PR2/PR3. Health check. OSEM and OpLev adjustment in PRM.

  • Type-C: Health check should be scheduled.

Status

  • Replacement of flip cables: EXT and BF temp.
  • TM height setting:
  • Oplev: Investigating the relation between laser and temperature. Adjustment for PRM. For SRs in the next week.
  • ACC:
  • Commissioning in air:
  • Commissioning in vacuum:
  • Acceptance check:
  • PF actuator: At the in-vacuum commissioning.
  • New vacuum pumps for V-chambers:
  • Heater control: Pending.
  • TMS: Window to EYT in the next week.

Discussion


VIS Meeting

Date: 2022/6/24 14:00-14:15

Participants: Takahashi, Uchiyama, Ushiba, Fabian, Tanaka, Aso, Washimi

Summary Report

Type-A

  • Monitored the build up. Height of the top chamber was changed by 1mm.

Type-B

  • We inspected SRM payload and chamber and we think we can exchange the small mirror after the installation of the mid-size baffle. When are we going to change it?

  • In SR3, we locked the suspension and First Contact was applied.
  • In the corresponding filter bank, I updated the information of the transfer function of the new geophone.

Type-Bp

  • In PR3 and PR2, we tested the Traverser limit switches.
  • In PRM, OSEMs H2 and H3 were close to the end of their linear ranges, therefore, we moved them. The payload is not as stable as we would've liked, and was disturbed when we installed the Traverser limit switches. See klog.
  • Health check of PRs.

Type-C

Electronics

Control

Schedule

  • Type-A: Monitor of pump down.
  • Type-B: MSB in SR3/SRM. OpLev setting.

  • Type-Bp: Health check.
  • Type-C:

Safety

Discussion

Travel Plans

(Date in Kamioka)

The week from 6/27

  • Takahashi: 6/27-7/1
  • Sato: 6/27-7/1
  • Hirata: 6/28-7/1

The week from 7/4

  • Takahashi: 7/5-8
  • Sato:
  • Hirata:

Next meeting

  • 2022/7/1(FRI)