Date: 2022/7/8 13:00 Date: 2022/7/8 13:00-13:30
Line 10: Line 10:
Participants: Participants: Takahashi, Uchiyama, Yokozawa, Ushiba, Kimura, Yasui, Aso, Hirata, Akutsu, Ikeda, Sato, Miyoki, Node
Line 15: Line 15:
 * IX: Offload of the F0. Adujustment of the OpLev for MN/PF.
 * EX: Adujustment of the OpLev for MN/PF.
 * IX: Offload of the F0. Adjustment of the OpLev for MN/PF.
 * EX: Adjustment of the OpLev for MN/PF.
Line 18: Line 18:
 * EY: Leak test. Repair of the GV. Offload of the GAS filters.  * EY: Leak test (Leak point was in the GV itself). Repair of the GV. Offload of the GAS filters.
Line 20: Line 20:
 * Type-Bp: Adujustment of the OpLev in PR2/PR3. Investigation of the PR2 suspension. Health check in the next week.  * Type-Bp: Adjustment of the OpLev in PR2/PR3. Investigation of the PR2 suspension. Health check in the next week.
Line 29: Line 29:
 * Commissioning in vacuum:  * Commissioning in vacuum: Keeping the X-arm. Health check in Y-arm.
Line 31: Line 31:
 * PF actuator: At the in-vacuum commissioning.
* New vacuum pumps for V-chambers: When should we implement the ion pumps? It is better to do before cooling.
 * New vacuum pumps: When should we implement the ion pumps? It is better to do before cooling.
Line 45: Line 44:
 * Cable replacement in EY.
Line 47: Line 48:
 * Visual inspection of PRs. PR2 only has a small hexagon between the BF and the IM.

Agenda/Minutes

Zoom Meeting


CRY+VIS Interface Meeting

Date: 2022/7/8 13:00-13:30

Participants: Takahashi, Uchiyama, Yokozawa, Ushiba, Kimura, Yasui, Aso, Hirata, Akutsu, Ikeda, Sato, Miyoki, Node

Post O3 Upgrade portal

Schedule

  • IX: Offload of the F0. Adjustment of the OpLev for MN/PF.

  • EX: Adjustment of the OpLev for MN/PF.

  • IY:
  • EY: Leak test (Leak point was in the GV itself). Repair of the GV. Offload of the GAS filters.
  • Type-B: Replacement of the mirror in SRM.
  • Type-Bp: Adjustment of the OpLev in PR2/PR3. Investigation of the PR2 suspension. Health check in the next week.

  • Type-C: Health check of the IMMT1/2 in the next week.

Status

  • Replacement of cables: EXT and BF temp.
  • TM height setting:
  • Oplev:
  • ACC:
  • Commissioning in air:
  • Commissioning in vacuum: Keeping the X-arm. Health check in Y-arm.
  • Acceptance check:
  • New vacuum pumps: When should we implement the ion pumps? It is better to do before cooling.
  • Heater control: Pending.
  • TMS:

Discussion


VIS Meeting

Date: 2022/7/8 14:00-

Participants:

Summary Report

Type-A

  • Cable replacement in EY.

Type-B

Type-Bp

  • Visual inspection of PRs. PR2 only has a small hexagon between the BF and the IM.

Type-C

Electronics

Control

Schedule

  • Type-A:
  • Type-B: Health check.
  • Type-Bp: Health check.
  • Type-C: Health check of IMMT1/2.

Safety

Discussion

Travel Plans

(Date in Kamioka)

The week from 7/11

  • Hirata: 7/12-15

The week from 7/18

  • Sato:
  • Hirata:

Next meeting

  • 2022/7/15(FRI)