Differences between revisions 1 and 2
Revision 1 as of 2022-10-06 17:08:34
Size: 1520
Comment:
Revision 2 as of 2022-10-07 11:41:45
Size: 1684
Comment:
Deletions are marked like this. Additions are marked like this.
Line 41: Line 41:
 * Testing the heater control in IY. The heater around the cross tube can affect the BF/F3 GAS drift.
 * Investigating the actuation noise in the ACCs in IX.
Line 46: Line 49:

Agenda/Minutes

Zoom Meeting


CRY+VIS Interface Meeting

Date: 2022/10/7 13:00-

Participants:

Post O3 Upgrade portal

Schedule

  • Type-A: Test of the heater control in IY. Evaluation of the ACCs in IX.
  • Type-B: Diagonalization of the IP LVDT-ACT in BS.
  • Type-Bp: Monitoring of the GAS filters during the evacuation in PRM.
  • Type-C: Monitoring of the IMMT suspensions during the evacuation.

Status

  • Replacement of cables: EXT remains.
  • TM height setting:
  • Oplev:
  • ACC: Evaluation.
  • Commissioning in vacuum:
  • Acceptance check: DropboxPaper

  • Vacuum system: Pump down of the IMMT-IFI-PRM chambers from 10/4. Leak check.
  • Heater control: Test in IY.
  • TMS: Finalization of TMSY.

Discussion


VIS Meeting

Date: 2022/10/7 14:00-

Participants:

Summary Report

Type-A

  • Testing the heater control in IY. The heater around the cross tube can affect the BF/F3 GAS drift.
  • Investigating the actuation noise in the ACCs in IX.

Type-B

Type-Bp

Type-C

Electronics

Control

Schedule

  • Type-A:
  • Type-B:
  • Type-Bp:
  • Type-C:

Safety

Discussion

Travel Plans

(Date in Kamioka)

The week from 10/10

  • Hirata: 10/12-14

The week from 10/17

  • Takahashi:
  • Sato:
  • Hirata:

Next meeting

  • 2022/10/14(FRI)

KAGRA/Subgroups/VIS/VISMinutes20221007 (last edited 2022-10-07 14:14:15 by RyutaroTakahashi)