Line 35: Line 35:
Date: 2022/10/7 14:00- Date: 2022/10/7 14:00-14:15
Line 37: Line 37:
Participants: Participants: Takahashi, Fabian, Lucia, Washimi, Tanaka, Ushiba, Aso
Line 45: Line 45:

---- /!\ '''Edit conflict - other version:''' ----

---- /!\ '''Edit conflict - other version:''' ----
 * In SRM, the ople windshield was partially removed in order to allow the search of leaks in the viewports. After such a work was done, the windshield put back again. No leak was found.
 * In the BS,
  * we diagonalized the LVDT L, T and Y degrees of freedom

---- /!\ '''Edit conflict - your version:''' ----
Line 59: Line 50:
---- /!\ '''End of edit conflict''' ----

---- /!\ '''Edit conflict - other version:''' ----

---- /!\ '''Edit conflict - your version:''' ----

---- /!\ '''End of edit conflict''' ----

---- /!\ '''Edit conflict - your version:''' ----

---- /!\ '''End of edit conflict''' ----
Line 78: Line 58:
 * Type-A:
 * Type-B:
 * Type-A: Investigation of ACCs.
 * Type-B: IP control in BS.

Agenda/Minutes

Zoom Meeting


CRY+VIS Interface Meeting

Date: 2022/10/7 13:00-13:25

Participants: Takahashi, Yokozawa, Sato, Mitsuhashi, Aso, Hirata, Ushiba, Akutsu, Tomaru, Ikeda

Post O3 Upgrade portal

Schedule

  • Type-A: Test of the heater control in IY. Evaluation of the ACCs in IX.
  • Type-B: Diagonalization of the IP LVDT-ACT in BS.
  • Type-Bp: Monitoring of the GAS filters during the evacuation in PRM.
  • Type-C: Monitoring of the IMMT suspensions during the evacuation. IM was touching the magnets in OSTM.

Status

  • Replacement of cables: EXT remains.
  • TM height setting:
  • Oplev: Investigation of input Y.
  • ACC: Evaluation.
  • Commissioning in vacuum: Beam lost in POP IR PD.
  • Acceptance check: DropboxPaper

  • Vacuum system: Pump down of the IMMT-IFI-PRM chambers from 10/4. The leak check will be continued in the next week and the next-next week.
  • Heater control: Test in IY.
  • TMS: Finalization of TMSY.

Discussion


VIS Meeting

Date: 2022/10/7 14:00-14:15

Participants: Takahashi, Fabian, Lucia, Washimi, Tanaka, Ushiba, Aso

Summary Report

Type-A

  • Testing the heater control in IY. The heater around the cross tube can affect the BF/F3 GAS drift.
  • Investigating the actuation noise in the ACCs in IX.

Type-B

  • In SRM, the oplev windshield was partially removed in order to allow the search of leaks in the viewports. After such a work was done, the windshield was put back again. No leak was found.
  • In the BS,
    • we diagonalized the LVDT and geophone L, T and Y degrees of freedom, and the actuation also. We should provide quantitative information on how low the current residual coupling is.
    • The calibration parameters of the geophones are not reported in the klog, nevertheless, the calibration TF currently used, seems to be working fine. Today, I'm trying to retrieve the values of the calibration parameters from TF measurements.

Type-Bp

Type-C

  • The IM is touching the magnets in the OSTM suspension. It will be recovered after the final alignment.

Electronics

Control

Schedule

  • Type-A: Investigation of ACCs.
  • Type-B: IP control in BS.
  • Type-Bp:
  • Type-C:

Safety

Discussion

Travel Plans

(Date in Kamioka)

The week from 10/10

  • Hirata: 10/12-14

The week from 10/17

  • Takahashi:
  • Sato:
  • Hirata:

Next meeting