Differences between revisions 16 and 19 (spanning 3 versions)
Revision 16 as of 2022-10-28 10:36:57
Size: 1809
Comment:
Revision 19 as of 2022-10-28 13:14:32
Size: 1928
Comment:
Deletions are marked like this. Additions are marked like this.
Line 8: Line 8:
Date: 2022/10/28 13:00- Date: 2022/10/28 13:00-13:10
Line 10: Line 10:
Participants: Participants: Takahashi, Uchiyama, Node, Mitsuhashi, Ushiba, Aso, Sato, Hirata, Ikeda, Yasui, Akutsu
Line 24: Line 24:
 * Commissioning:
 * Vacuum system: Cooling problem in EXC? GV Opening in EYT on 10/31. Pump replacement in EYT on 11/4.
 * Commissioning: Lock of the PR cavity.
 * Vacuum system: Cooling problem in EXC? GV opening in EYT on 10/31. Moving of the dry pump in EYT on 11/4.

Agenda/Minutes

Zoom Meeting


CRY+VIS Interface Meeting

Date: 2022/10/28 13:00-13:10

Participants: Takahashi, Uchiyama, Node, Mitsuhashi, Ushiba, Aso, Sato, Hirata, Ikeda, Yasui, Akutsu

Acceptance check document

Status

  • Type-A:
  • Type-B: Optimization of the IP controls (Blending filter, Sensor correction, Noise measurement).
  • Type-Bp: Decoupling of TM/BF in PRM.
  • Type-C:

Other items

  • Replacement of cables: EXT remains.
  • Oplev: Windshield in PRM.
  • ACC:
  • Commissioning: Lock of the PR cavity.
  • Vacuum system: Cooling problem in EXC? GV opening in EYT on 10/31. Moving of the dry pump in EYT on 11/4.
  • Heater control: Test in IY. GAS drift was large in EY from 10/25.
  • TMS:

Discussion


VIS Meeting

Date: 2022/10/28 13:30-

Participants:

Summary Report

Type-A

  • GAS drift was large in EY from 10/25.

Type-B

  • SR3: With new geophone inter-calibration factors, Lucia implemented the inertial damping and updated Guardian.
  • SR2:
    • Lucia implemented inertial damping and upated Guardian.
    • Fabián wrote a Jupyter notebook based on Terrence's tutorial for blending geophone and LVDT using the methods he developed. It's still a work on progress.

Type-Bp

  • PRM: Ushiba-san did diagonalization of the BF and oplev.

Type-C

Electronics

Control

Schedule

  • Type-A:
  • Type-B: Optimization of IP controls.
  • Type-Bp:
  • Type-C:

Safety

Discussion

Travel Plans

(Date in Kamioka)

The week from 10/31

  • Hirata: ?

The week from 11/7

  • Takahashi: 11/7-10
  • Aso: 11/7-10

Next meeting

  • 2022/11/4(FRI) 13:30

KAGRA/Subgroups/VIS/VISMinutes20221028 (last edited 2022-10-28 13:14:32 by RyutaroTakahashi)