Agenda/Minutes

Zoom Meeting


CRY+VIS Interface Meeting

Date: 2022/11/18 13:00-

Participants:

Acceptance check document

Status

  • Type-A: Implementation of the new blending filter in EX, IY, IX. Update of the payload controls in EX, EY.
  • Type-B: Test of the vertical sensor correction in SR2, BS.
  • Type-Bp:
  • Type-C: Finalization of OMMT-OMC.

Other items

  • ITM fabrication: Chip.
  • Replacement of cables: EXT remains.
  • Oplev:
  • ACC:
  • Commissioning:
  • Vacuum system: Closing of the OMMT-OMC chambers in the next week. GV opening in EYT after 11/15.
  • Heater control:
  • TMS:

Discussion


VIS Meeting

Date: 2022/11/18 13:30-

Participants:

Summary Report

Type-A

Type-B

Type-Bp

Type-C

  • Health check of the OMMT1/2/OSTM suspensions. The measured TFs look healthy. Some OSEMs deviated from the optimal position.

Electronics

Control

Schedule

  • Type-A:
  • Type-B:
  • Type-Bp:
  • Type-C: Closing and evacuation of the OMMT-OMC chambers.

Safety

Discussion

Travel Plans

(Date in Kamioka)

The week from 11/21

  • Hirata: ?

The week from 11/28

  • (F2F meeting: 11/30-12/1)

Next meeting

  • 2022/11/25(FRI) 13:30