Size: 1561
Comment:
|
Size: 1815
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 8: | Line 8: |
Date: 2022/11/18 13:00- | Date: 2022/11/18 13:00-13:35 |
Line 10: | Line 10: |
Participants: | Participants: Takahashi, Uchiyama, Aso, Mitsuhashi, Ushiba, Ikeda, Sato, Yasui, Akutsu, Hirata |
Line 34: | Line 34: |
Date: 2022/11/18 13:30- | Date: 2022/11/18 13:35-13:45 |
Line 36: | Line 36: |
Participants: | Participants: Takahashi, Uchiyama, Aso, Mitsuhashi, Ushiba |
Line 40: | Line 40: |
* Implementation of the new blending filter in EX, IY, IX. |
|
Line 41: | Line 43: |
* Test of the vertical sensor correction in SR2, BS. |
Contents
Agenda/Minutes
CRY+VIS Interface Meeting
Date: 2022/11/18 13:00-13:35
Participants: Takahashi, Uchiyama, Aso, Mitsuhashi, Ushiba, Ikeda, Sato, Yasui, Akutsu, Hirata
Status
- Type-A: Implementation of the new blending filter in EX, IY, IX. Update of the payload controls in EX, EY.
- Type-B: Test of the vertical sensor correction in SR2, BS.
- Type-Bp:
- Type-C: Finalization of OMMT-OMC. Monitoring during the evacuation in the next week.
Other items
- ITM fabrication: Chip.
- Replacement of cables: EXT remains.
- Oplev:
- ACC:
- Commissioning:
- Vacuum system: Closing of the OMMT-OMC chambers in the next week. GV opening in EYT after 11/15.
- Heater control:
- TMS:
Discussion
VIS Meeting
Date: 2022/11/18 13:35-13:45
Participants: Takahashi, Uchiyama, Aso, Mitsuhashi, Ushiba
Summary Report
Type-A
- Implementation of the new blending filter in EX, IY, IX.
Type-B
- Test of the vertical sensor correction in SR2, BS.
Type-Bp
Type-C
- Health check of the OMMT1/2/OSTM suspensions. The measured TFs look healthy. Some OSEMs deviated from the optimal position.
Electronics
Control
Schedule
- Type-A:
- Type-B:
- Type-Bp:
- Type-C: Monitoring of the OMMT1/2/OSTM suspensions during the evacuation.
Safety
Discussion
Travel Plans
(Date in Kamioka)
The week from 11/21
The week from 11/28
- (F2F meeting: 11/30-12/1)
Next meeting