Line 44: Line 44:
Date: 2023/9/1 10:00- Date: 2023/9/1 10:00-11:20
Line 46: Line 46:
Participants: Participants: Takahashi, Sato, Mitsuhashi, Tanaka, Hirata, Aso
Line 50: Line 50:
 * Adjustment of the damping control for ITMX.

Agenda/Minutes

Zoom Meeting


CRY+VIS Interface Meeting

Date: 2023/9/1 13:00-

Participants:

Acceptance check document

Suspensions

  • Type-A:
  • Type-B:
  • Type-Bp:
  • Type-C:

Other items

  • Oplev:
  • ACC:
  • Commissioning:
  • Vacuum system:
  • Heater control:
  • TMS:

Post O4a

  • Measurements of the DAC noise: Type-C.
  • Measurements on the sensor correction in SR2: Response from Terrence.
  • Optimization of the damping control in PRs: Measurements 2 days, Test 3 days.
  • IP control with the ACCs: One more test is necessary.
  • In-vacuum accelerometer for IOO: Leak test of the pod is planed.
  • Hight adjustments of Type-A in the cooling: Monitor from 9/8.
  • Temperature control for the Oplev: Prepare for IXC and EXC.
  • TM cooling: Schedule.
  • IM heater: Installation for IX in the week of 9/4.
  • Summary of cooling.

Discussion


VIS Meeting

Date: 2023/9/1 10:00-11:20

Participants: Takahashi, Sato, Mitsuhashi, Tanaka, Hirata, Aso

Summary Report

Type-A

  • Adjustment of the damping control for ITMX.

Type-B

Type-Bp

Type-C

  • Damping of the OMC suspension.
    • Test of the blade damper.
    • Design of the flexible pendulum damper.

Electronics

Control

R&D

  • TAMA-SAS experiment: Assembly of the Roberts Linkage.

Schedule

  • TAMA-SAS experiment.
  • Finalization of the OMC damper.

Toward O5

Discussion

Next meeting

  • 2023/9/8 10:00-

KAGRA/Subgroups/VIS/VISMinutes20230901 (last edited 2023-09-01 13:16:01 by RyutaroTakahashi)