<<TableOfContents(3)>>

= Agenda/Minutes =
[[https://zoom.us/j/203743987|Zoom Meeting]]

----------
= CRY+VIS Interface Meeting =
Date: 2023/10/6 13:00-13:30

Participants: Takahashi, Uchiyama, Aso, Yokozawa, Sato, Miyoki, Akutsu, Ushiba, Mitsuhashi

[[https://paper.dropbox.com/folder/show/AcceptanceTest-e.1gg8YzoPEhbTkrhvQwJ2zzo3dHVh5sJGieDgbm2n3h60mGqotBeE|Acceptance check document]]

== Suspensions ==
 * Type-A: Offload in IX. Test of IP control with ACCs in IY. Update of damping control.
 * Type-B: Update of damping control.
 * Type-Bp: 
 * Type-C: 

== Other items ==
 * Oplev: Centering of the MN oplev in EY.
 * ACC: 
 * Commissioning: 
 * Vacuum system: Investigation of the TMP in X-27. GV remote operation was implemented.
 * Heater control: 
 * TMS: 

== Post O4a ==
 * Measurements of the DAC noise: Type-C.
 * Optimization of the damping control in PRs: Test for PR3 again.
 * IP control with the ACCs: One more test.
 * In-vacuum accelerometer for IOO: Leak test of the geophone pods. The new pod passed for the OMC chamber.
 * Height adjustments of Type-A in the cooling: Monitoring.
 * Temperature control for the Oplev: Installation in IXC and EXC was finished.
 * TM cooling: Schedule.
 * IM heater: Installed to EX.
 * OMC damper: The parts have been ordered. Vent on 10/13.

== Discussion ==

----------