Line 22: | Line 22: |
* Change of the number of stages from 3 to 1-2. The performance will be tested using the TAMA stack. | * Change of the stages from 3 to 1-2. The performance will be tested using the TAMA stack. |
Contents
VIS Meeting
Date: 2024/8/16 10:00-
Participants:
Topics
Type-A
- IP controls using ACCs
Test of the 50mHz blending in EY. The performance of the H2 FLDACC is not good.
Type-B/Bp
- BF damper for Type-B.
- IP for Type-Bp.
Type-C
- OMC stack
- Change of the stages from 3 to 1-2. The performance will be tested using the TAMA stack.
- Investigation of soft rubbers.
- Active isolation table for OMC by ATC.
- Design in 2024FY, Procurement and assembly in 2025FY, Evaluation and installation from 2026 spring-summer.
R&D
- Protection from earthquakes
Application for R7 Kakenhi (Memo)
Discussion
Next meeting