Contents
VIS Meeting
Date: 2025/1/17 10:00-
Participants:
Topics
Type-A
- Height adjustment during the cooling.
- ACCs for the IP controls.
- Preparing for the stand-alone test bench with DGS in Mitaka. Ikeda-san has set the DGS up in the ATC lab.
Type-B/Bp
- Enclosure for the SG card into an independent box.
- Asking Tanaka-san.
- Yaw damper for Type-B.
- IP for Type-Bp.
Type-C
- Active isolation table for OMC.
Sato-san is checking the fitting condition of the TMS isolator to the OMC chamber (update).
- Vibration in the IFI chamber
R&D
Discussion
Next meeting
- 2025/1/31 10:00-