VIS Meeting

Date: 2025/1/31 10:00-

Zoom

Participants:

Topics

Type-A

  • Height adjustment during the cooling.
    • Total (duct + TM) height change was 1~3mm.
  • ACCs for the IP controls.
    • Preparing for the stand-alone test bench with DGS in Mitaka. Ikeda-san has set the DGS up in the ATC lab.

Type-B/Bp

  • Enclosure for the SG card into an independent box.
    • Tanaka-san will make a prototype.
  • Yaw damper for Type-B.
    • One set should be tested in SRM around autumn 2025.
  • IP for Type-Bp.

Type-C

  • Active isolation table for OMC.
    • Sato-san is checking the parameters of the TMS isolator for OMC. He calculated the blade springs.
    • Asking Marutsu to make geophone pre-amp boards.
  • Vibration in the IFI chamber
    • Fixing the STM is planned for late February.
  • Small Type-C suspensions with mini-GAS.

R&D

Discussion

  • Task list for authorship 2025.
    • Management of the group
    • Commissioning of the suspensions toward O4c
    • Maintenance of the suspensions during O4c
    • Preparation for upgrade toward O5
    • Control upgrade
    • Software development

Next meeting

  • 2025/2/14 10:00-