Size: 852
Comment:
|
← Revision 6 as of 2025-11-07 10:24:13 ⇥
Size: 936
Comment:
|
| Deletions are marked like this. | Additions are marked like this. |
| Line 5: | Line 5: |
| Date: 2025/11/07 10:00- | Date: 2025/11/07 10:00-10:20 |
| Line 9: | Line 9: |
| Participants: | Participants: Aso, Ushiba, Sato, Akutsu, Yokozawa, Takahashi |
| Line 27: | Line 27: |
| * The new geophone pod has been delivered. | * The new geophone pod has been delivered. A leak test should be performed. |
Contents
VIS Meeting
Date: 2025/11/07 10:00-10:20
Participants: Aso, Ushiba, Sato, Akutsu, Yokozawa, Takahashi
Topics
Type-A
- ACCs for the IP controls.
- Evaluating the FLDACC with DGS in ATC.
Preparing for three ACCs (preassembly).
Type-B/Bp
- IRM damper for Type-B.
- Installation in SRM is scheduled on 3/9-19.
- Enclosure for the SG card in an independent box.
- Preparing for the boxes with a 1U rack panel.
- IP for Type-Bp.
- Started a design.
Type-C
- Active isolation table for OMC.
- The new geophone pod has been delivered. A leak test should be performed.
- Sato-san is checking the coupling due to the blade springs.
- Small Type-C suspensions with mini-GAS.
R&D
Discussion
Next meeting
- 2025/11/21 10:00-