Differences between revisions 5 and 6
Revision 5 as of 2025-11-06 14:36:25
Size: 852
Comment:
Revision 6 as of 2025-11-07 10:24:13
Size: 936
Comment:
Deletions are marked like this. Additions are marked like this.
Line 5: Line 5:
Date: 2025/11/07 10:00- Date: 2025/11/07 10:00-10:20
Line 9: Line 9:
Participants: Participants: Aso, Ushiba, Sato, Akutsu, Yokozawa, Takahashi
Line 27: Line 27:
  * The new geophone pod has been delivered.   * The new geophone pod has been delivered. A leak test should be performed.


VIS Meeting

Date: 2025/11/07 10:00-10:20

Zoom

Participants: Aso, Ushiba, Sato, Akutsu, Yokozawa, Takahashi

Topics

Type-A

  • ACCs for the IP controls.
    • Evaluating the FLDACC with DGS in ATC.
    • Preparing for three ACCs (preassembly).

Type-B/Bp

  • IRM damper for Type-B.
    • Installation in SRM is scheduled on 3/9-19.
  • Enclosure for the SG card in an independent box.
    • Preparing for the boxes with a 1U rack panel.
  • IP for Type-Bp.
    • Started a design.

Type-C

  • Active isolation table for OMC.
    • The new geophone pod has been delivered. A leak test should be performed.
    • Sato-san is checking the coupling due to the blade springs.
  • Small Type-C suspensions with mini-GAS.

R&D

Discussion

Next meeting

  • 2025/11/21 10:00-

KAGRA/Subgroups/VIS/VISMinutes20251107 (last edited 2025-11-07 10:24:13 by RyutaroTakahashi)