VIS Meeting
Date: 2025/11/21 10:00-
Participants:
Topics
Type-A
- Oscillation of ITMX.
ITMX had a large oscillation around 1Hz due to the rubbing of the F3 keystone. The setpoints of F1 and F3 were changed (klog).
- ACCs for the IP controls.
- Evaluating the FLDACC with DGS in ATC.
- Preparing for three ACCs.
Type-B/Bp
- IRM damper for Type-B.
- Installation in SRM is scheduled on 3/9-19.
- Enclosure for the SG card in an independent box.
- Preparing for the boxes with a 1U rack panel.
- IP for Type-Bp.
- Started a design.
Type-C
- Active isolation table for OMC.
- The new geophone pod is assembled. A leak test should be performed.
- Sato-san is designing the fishing rod.
- Small Type-C suspensions with mini-GAS.
R&D
Discussion
Next meeting