Line 5: Line 5:
Date: 2026/2/27 11:00- Date: 2026/2/27 11:00-11:15
Line 9: Line 9:
Participants: Participants: Takahashi, Washimi, Sato, Akutsu, Yokozawa


VIS Meeting

Date: 2026/2/27 11:00-11:15

Zoom

Participants: Takahashi, Washimi, Sato, Akutsu, Yokozawa

Topics

Type-A

  • Oplev
    • Check the amount of light during the power outage.
  • ACCs for the IP controls.
    • TF measurements of the folded pendulum are necessary.

Type-B/Bp

  • Installation in SRM
    • Notion page

    • The detailed schedule is here.

    • Mirror replacement: The mirror holder was checked (klog).

    • IRM damper: The assembled parts are ready at the site.
    • FLDACC: The folded pendulums are reassembled at the site (klog).

  • SG card box.
    • One box was installed in the SRM rack.
  • IP for Type-Bp.
    • Started a design.

Type-C

  • Active isolation table for OMC.
    • Notion page

    • The prototype of the maraging blades is under manufacturing.
  • Small Type-C suspensions with mini-GAS.

R&D

  • Python version of Sumcom by Fabian.
  • Modification of the Type-A tower toward O6.

Discussion

Next meeting

  • 2026/3/27 10:00-

KAGRA/Subgroups/VIS/VISMinutes20260227 (last edited 2026-02-27 11:15:07 by RyutaroTakahashi)