ISC Meeting on 2016/1/25
14:00 - 15:00 on SeeVogh
Participants:
- Schedule for iKAGRA (Aso)
- Installation of the analog electronics
- Installation of the detection optics
- Digital system integration
- Initial alignment procedure
- Electronics Preparation Status (Michimura, Aso)
- RF PD (Aso, Doi)
- Cable assembly
- RF low loss cables with N connectors: order status
- Diff-to-single cables
- we have purchased all the other ISC cables
- Magnet noise
- Magnetometer requirement(Michimura)
- FFT simulation (H. Yamamoto, Hirose)
- Next meting 2016/2/16?