= ISC Meeting on 2017/1/23 14:00 - 15:00 =
Participants:

=== Next meeting ===
2017/2/20 14:00 - 15:00 ?

[[LCGT/subgroup/ifo/ISC/Meetings|back to Meetings page]]

== Agenda ==
 * bKAGRA Phase 1 optical configuration study [Michimura]
  * summary: [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5595|JGW-T1605595]]
  * ASC [Enomoto]
   * noise study by Noise``Budget [Enomoto]
    * Enomoto volunteered to do ASC Noise``Budget; meeting on Sept 27
     * trouble on number of licenses and library links, but finally able to run example model
   * effect on WFS from RF HOMs [who?]
  * check if reference spheres for PR mirrors are available at Caltech [Hirose]
   * 9.0m (CC), 11.5m (CC), 6.5m (CC), 5.0m (CC), 34m (CX), 36m (CX) were available
   * PR2/SR2 is -3.0764m/-2.9872m and PR3/SR3 is 24.9165m. Maybe 5.0m TS can be used for PR2/SR2.
   * what about PR3/SR3, PRM/SRM?
  * check if IMC length stability and others are compatible with 3-km PRMI [Michimura]

 * bKAGRA Phase 1 initial alignment / commissioning plan [Michimura]: [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5595|JGW-T1605595]]
  * procedure summarized in [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5692|JGW-T1605692]] {*}
   * presented at Chief Meeting on Sept 26
   * '''TMS BRT alignment could be tough''' because of faint transmitted beam after ETM installation (~0.25uW)
    * use green?
     * BS transmission for green is S:99.40% P:97.85% at 45 deg
     * 100 mW green beam from PR gives ~0.12 mW at ETMY transmission
   * '''check optical layout [Michimura->Aso]'''
  * check if ETM transmitted beam can go through when ETM is not installed [Michimura] {*}
   * ETM transmitted beam can reach EXT/EYT when no wedge (5.6 mm shifted from the center of EXT/EYT)
   * EXT/EYT tanks/ducts are installed considering ETM wedge effect
  * wide/narrow angle baffles for Phase 1? [Akutsu] {*}
   * talk with Uchiyama & Saito on Sept 27-28?
    * as for NAB: install if possible, but maybe without suspension
    * as for WAB: try WAB with suspension at EXC, maybe no installaton at EYC
    * first priority is cryopayloads and evacuation/cool-down
  * camera to see ETM HR surface [Akutsu, Inoue, Kokeyama] {*}
   * CAL report ([[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5737|JGW-G1605737]])
   * wide angle baffle modification is needed to see the ETM edge
  * how to extract AS beam should be fixed by MIF
   * extract SR2 reflected beam at SR3 chamber (decided at the meeting on Sept 13) {*}
  * IMMT1-IMMT2 beam collimation plan not yet [MIF]
  * green alignment plan not yet [MIF]
  * TMS possible without ITM? [Akutsu->Michimura]
   * check q-parameter at TMS witouht ITM

 * bKAGRA Phase 1 analog electronics ([[KAGRA/Subgroups/MIF/AEL|Analog Electronics for ISC]]) [Michimura]
  * Quad IQ Demodulator heat-up issue
   * 1st stage amp is heating up
   * '''we have to decide if we need 1st stage amp or not'''
  * Quad IQ Demodulator LSC to ASC<<BR>>
   * mass production will be taken care by AEL
   * 4-way splitter (Mini-Circuits ZFSC-4-1-S+) arrived at Kamioka -> Mozumi office loft
  * RF Distribution Amplifier [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4460|JGW-D1504460]]
   * we will omit RF monitor for now, and add them later
   * front/rear panels, RF amps, 8-way splitters, couplers, cables and connectors at Mozumi office loft
  * RF Frequency Doubler
   * what's the frequency? [Kamiizumi->Michimura] {*}
    * thought used for 2*f1,2*f2, but aLIGO uses them for ALS
  * Requested Universal Whitening Filter with DC Power to AEL ([[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5839|JGW-T1605839]]) {*}
   * see [[KAGRA/Subgroups/AOS/DCQPDDriverList|DCQPDDriverList]] (see, also, [[KAGRA/Subgroups/AOS/DCQPDList|DCQPDList]])
   * need to coordinate with subgroups (MIF, IOO, AOS, VIS, CRY)

 * RF PDs and RF QPDs
  * RF PD / RF QPD noise and transimpedance characterization
   * we need permanent test bench
  * RF PD modification [who?]
   * fix DC path
   * solve single supply issue (RF PDs easily break when accidentally supplied with single)
   * fix plugs so that Dsub 9pin cable fixes better

 * RF Cables
  * ordered 5m/10m SMA cables for IMC WFS ([[https://docs.google.com/spreadsheets/d/1VPkv64gDrbhSX4LiO5aNc-miSf3h3pl1dRQPKUhnuCs|List of cables]]) {*}

 * Output optical tables [Michimura] ([[KAGRA/Subgroups/IOO/OutputTables|OutputTables wiki]])
  * vacuum optics to extract beams for each port (except for REFL and AS DC) and related beam shutters will also be MIF task
  * EXT/EYT tables
   * table height fixed; they will be put on mortar surface
   * isolation floor cutting and mortar application plan sent to Mirapro
   * installation on Mar 2017, along with installation of EXT/EYT chambers?
  * POS and AS tables
   * table height fixed; POS will be on concrete surface, AS will be on mortar surface

 * Arm Length Stabilization plan ([[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5353|JGW-T1605353]])
  * Noise``Budget [Kambara]
   * results agreed with Tatsumi Simulink model
   * include fiber noise (fiber setup is different from Tatsumi model)
    * fiber length? how to do the wiring? {*}
    * ask LIGO people how they are fixing the cables {*}
     * no special vibration / heat treatment [from Kawabe]
   * include phase noise from mirror vibration for IR beat setup (it is one of the limiting noise source for aLIGO)
   * schedule and plan for the procurement of circuits should be fixed soon
    * keep in touch with AEL group
   * local oscillator phase noise ([[https://granite.phys.s.u-tokyo.ac.jp/wiki/Lab/index.php?LCGTALSPhaseNoise|calculation method]]) {*}
    * discuss with Aso and redo calculation

 * Magnetic noise, actuator noise calculation for cryogenic payload
  * magnetic noise [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=4459|JGW-T1504459]] [Shimoda]
  * actuator noise and range calculation on going [Miyamoto([[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5746|JGW-G1605746]]), Okutomi] {*}
   * TM actuator efficiency should be less than 1.5 mN/A from noise point of view
   * if 1.5 mN/A, RMS velocity should be smallter than 0.04 um/sec
    * simulation on-going [Okutomi]

-----
 * Requirement on actuator range for IMMT [Ohishi] {*}
  * magnet size: 2 mm dia, 5 mm long
  * coil turns: 39?
  * this gives 4 times larger efficiency than the IMC coil efficiency
  * IMMT resonant frequencies: pitch ~1.8 Hz, yaw ~1.5 Hz
  * this gives 50/sqrt(2) mm * (1.4e-3 N/A * 4) * 4 magnets * 1/80 A/V / 9.6e-4 kg*m^2^  / (2*pi*1.8 Hz)^2^ = 8e-5 rad/V efficiency in pitch
  * is this enough?
   * IMC mirror (Type-C + stack) drift in yaw was less than 1 mrad/month, pitch was much less [Nakano]
   * iKAGRA ETM (Type-C w/o stack) drift was ???

 * RF generation scheme [Michimura]
  * f1 = 3/8*f2, f3 = 10/8*f2
  * we need 2*f1, 2*f2, f3-f1, f3-f2 as well
  * use harmonics generator (x2, x3, x6, x8, x10, x16 for f2/8 = 5.62698725 MHz (FSR for IMC))
   * seeking for vendors
  * MIF and IOO agreed to use 13.78 MHz (~= f2/8*2.45) for IMC sideband ([[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5493|JGW-T1605493]])
  * MIF agreed to use 32 MHz and 33 MHz for ALS sidebands [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5626|JGW-T1605626]]
  * may be IMC sideband (and ALS sidebands) should also needs to be phase locked with f1/f2/f3 to avoid "whistling noise"
  * in case of KAGRA, we don't need Frequency Doubler or Frequency Divide By Two for ALS {*}
   * is this true?

 * bKAGRA optical layout around PRC
  * POY clipping issue will be solved by modifying PR3 optical bench suspension [Shoda]
  * we need layout CAD for POY pickoff mirror, POP pickoff mirror to design baffles
   * budget for baffles around POY and POP were shifted to next FY [SEO]

 * viewport quality for GV between SRM and OMMT [Akutsu]
  * aLIGO case: SRM-OFI-viewport, KAGRA case: SRM-viewport-OMMT-OFI
  * aLIGO viewport is always closed
  * '''if we need super quality viewport, we have to decide soon'''

 * BS baffle could make contract defect? ([[https://dcc.ligo.org/LIGO-T1000090|LIGO-T1000090]])
  * ask Akutsu and Hiro
  * BS has 370 mm dia and beam at BS is 2*36 mm dia. So, it should be in principle OK. But recoil mass aperture should be considered.
 * bKAGRA ISC cabling [Michimura/Doi]
  * announced to IOO mailing list
  * need to update the cabling diagram
 * Mirror absorption measurement status [Hirose]
 * Output optics status [Somiya]
  * suspensions for OMMT1/2 is same as IMMT1/2 (driver list for now: [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5334|JGW-L1605334]])
  * we have to make vacuum compatible PD/QPD for OMC by 2018.3
  * beam shutter: prototype done, AR coating and driver circuit design not yet
  * OMC suspension is TMS-like plate spring and single pendulum [Somiya]
 * Task list update ([[KAGRA/Subgroups/MIF/TaskList|TaskList]]) [Michimura]
cancelled

cancelled

KAGRA/subgroup/ifo/MIF/Minutes20170123 (last edited 2016-12-14 09:53:04 by YutaMichimura)