Size: 1075
Comment:
|
Size: 2633
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 2: | Line 2: |
Participants: | Participants: Aso, Kokeyama, Enomoto, Koji Nagano, Michimura(eZuce meeting) |
Line 9: | Line 9: |
== Minutes == * PSL EOM Layout re-consideration [Enomoto] * delay-line length decided to be 2.66 m (instead of 8.88 m) * Modulation index needed at each EOM is less than measured maximum index by Uehera * Optickle simulation by Kohei Yamamoto? * start with hand calculation, simple setups, and then to full IFO simulation * OFI and OMC status * we need design review first! |
|
Line 10: | Line 20: |
* EOM Layout re-consideration [Enomoto] ([[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=6748|JGW-T1706748]]) | * PSL EOM Layout re-consideration [Enomoto] ([[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=6748|JGW-T1706748]]) |
Line 15: | Line 25: |
* Requirement on carrier power loss? |
|
Line 18: | Line 30: |
* Needs to update lock acquisition section (see [KAGRA/subgroup/ifo/MIF/Minutes20170410|ISC Meeting minutes 20170410]]) [Michimura] | * Needs to update lock acquisition section (see [[KAGRA/subgroup/ifo/MIF/Minutes20170410|ISC Meeting minutes 20170410]]) [Michimura] * RF Doubler Requirement [Michimura] * Used for generating 2*f1 and 2*f2 for sideband power monitor * Final requirements from ISC are * Input Frequency: 16.88 ± 0.1 MHz, 45.02 ± 0.1 MHz (two kinds) * Input Level: +10 ± 1 dBm * Multiplication Factor: x2 * Output Frequency: 33.76 ± 2 MHz, 90.03 ± 2 MHz * Output Level: +13 ± 2 dBm * Harmonics: < -25 dBc (as small as possible) * Sub-Harmonics: < -40 dBc (as small as possible) * Noise Floor: -170 dBc/Hz (at frequency as low as possible) * [[http://www.wenzel.com/model/diode-doubler-lndd/#tabs|Wenzel LNDD]] meets requirement * Waiting for more detailed spec sheet [Kamiizumi] * OFI and OMC status? [Somiya] * look for OFI with larger aperture [Somiya] * output optics task sharing status? * OMC baseplate issue? * bKAGRA Phase 1 initial alignment / commissioning plan [Michimura]: [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5595|JGW-T1605595]] * needs to be updated based on updated schedule |
ISC Meeting on 2017/6/5 14:00 - 15:00
Participants: Aso, Kokeyama, Enomoto, Koji Nagano, Michimura(eZuce meeting)
Next meeting
2017/6/19 14:00 - 15:00
Minutes
- PSL EOM Layout re-consideration [Enomoto]
- delay-line length decided to be 2.66 m (instead of 8.88 m)
- Modulation index needed at each EOM is less than measured maximum index by Uehera
- Optickle simulation by Kohei Yamamoto?
- start with hand calculation, simple setups, and then to full IFO simulation
- OFI and OMC status
- we need design review first!
Agenda
PSL EOM Layout re-consideration [Enomoto] (JGW-T1706748)
- Delay-line length was wrong.
- Relative modulation phase between f1 AM and PM considered.
- Checked modulation depth availability.
- Optickle simulation by Kohei Yamamoto?
- Requirement on carrier power loss?
Actuator noise modeling [Michimura,Miyamoto] (JGW-T1503453)
Updated magnet size for cryopayload marionette (ActuatorDesign wiki)
- Needs to implement frequency noise, but FSS modeling with ALS is complicated [student!]
Needs to update lock acquisition section (see ISC Meeting minutes 20170410) [Michimura]
- RF Doubler Requirement [Michimura]
- Used for generating 2*f1 and 2*f2 for sideband power monitor
- Final requirements from ISC are
- Input Frequency: 16.88 ± 0.1 MHz, 45.02 ± 0.1 MHz (two kinds)
- Input Level: +10 ± 1 dBm
- Multiplication Factor: x2
- Output Frequency: 33.76 ± 2 MHz, 90.03 ± 2 MHz
- Output Level: +13 ± 2 dBm
Harmonics: < -25 dBc (as small as possible)
Sub-Harmonics: < -40 dBc (as small as possible)
- Noise Floor: -170 dBc/Hz (at frequency as low as possible)
Wenzel LNDD meets requirement
- Waiting for more detailed spec sheet [Kamiizumi]
- OFI and OMC status? [Somiya]
- look for OFI with larger aperture [Somiya]
- output optics task sharing status?
- OMC baseplate issue?
bKAGRA Phase 1 initial alignment / commissioning plan [Michimura]: JGW-T1605595
- needs to be updated based on updated schedule
See this page for other agendas.