Line 32: Line 32:
  * needs to be updated based on updated schedule   * updated based on current schedule
   * ETMX and ETMY cryopayload installation almost at the same time
   * MICH lock at room temperature before cooling down (instead of cooling down ETMY first)
   * AS cannot be used for room temperature MICH lock (SR3 not ready)
   * SR2 won't be ready by the end of March 2018

ISC Meeting on 2017/6/19 14:00 - 15:00

Participants: (eZuce meeting)

Next meeting

2017/7/3 14:00 - 15:00

back to Meetings page

Agenda

  • PSL EOM Layout re-consideration [Enomoto] (JGW-T1706748)

    • Delay-line length decided to be 2.66 m (instead of 8.88 m)
    • Modulation phase between f1 AM and PM is always aligned (we need this to be aligned)
    • Modulation index needed at each EOM is less than measured maximum index by Uehera (JGW-T1605611)

    • Optickle simulation by Kohei Yamamoto
      • simulation on imperfections (MZ arm asymmetry, MZ lock, EOM phase difference control etc.)
      • start with hand calculation, simple setups, and then to full IFO simulation
      • meeting with him on June 6.
    • Requirement on carrier power loss?
  • OFI and OMC status? [Somiya]
    • look for OFI with larger aperture [Somiya]
    • output optics task sharing status?
    • OMC baseplate issue?
    • design review on June 26
  • Actuator noise modeling [Michimura,Miyamoto] (JGW-T1503453)

    • Updated magnet size for cryopayload marionette (ActuatorDesign wiki)

    • Needs to implement frequency noise, but FSS modeling with ALS is complicated [student!]
    • Needs to update lock acquisition section (see ISC Meeting minutes 20170410) [Michimura]

  • bKAGRA Phase 1 initial alignment / commissioning plan [Michimura]: JGW-T1605692

    • updated based on current schedule
      • ETMX and ETMY cryopayload installation almost at the same time
      • MICH lock at room temperature before cooling down (instead of cooling down ETMY first)
      • AS cannot be used for room temperature MICH lock (SR3 not ready)
      • SR2 won't be ready by the end of March 2018