= ISC Meeting on 2017/6/19 14:00 - 15:00 = Participants: Hirose, Aso, Kokeyama, Michimura (eZuce meeting) === Next meeting === 2017/7/3 14:00 - 15:00 [[LCGT/subgroup/ifo/ISC/Meetings|back to Meetings page]] == Minutes == * Actuator noise modeling [Michimura] * Noise from heat links is one of the most interesting issues to be discussed * Ask people about the heat link vibration estimation status * bKAGRA Phase 1 initial alignment * Poke Akutsu for baffle PD for initial alignment use [Michimura] * IR/green steering mirrors * No objections for proposed mirror specs == Agenda == * PSL EOM Layout re-consideration [Enomoto] ([[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=6748|JGW-T1706748]]) * Delay-line length decided to be 2.66 m (instead of 8.88 m) * Modulation phase between f1 AM and PM is always aligned (we need this to be aligned) * Modulation index needed at each EOM is less than measured maximum index by Uehera ([[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5611|JGW-T1605611]]) * Optickle simulation by Kohei Yamamoto * simulation on imperfections (MZ arm asymmetry, MZ lock, EOM phase difference control etc.) * start with hand calculation, simple setups, and then to full IFO simulation * meeting with him on June 6. * Requirement on carrier power loss? * Comment from Stefan Ballmer {*} * Similar calculation was done in LIGO in the past. Displacement noise requirement for MZ was tough (~1e-14 m/rtHz). * Any in-air interferometer suffer from jitter and frequency noise which cannot be suppressed. * OFI and OMC status? [Somiya] * look for OFI with larger aperture [Somiya] * output optics task sharing status? * OMC baseplate issue? * design review on June 26 at Titech {*} * Actuator noise modeling [Michimura,Miyamoto] ([[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=3453|JGW-T1503453]]) * Updated magnet size for cryopayload marionette ([[KAGRA/Subgroups/VIS/ActuatorDesign|ActuatorDesign wiki]]) * Updated lock acquisition section to derive velocity requirements for suspensions (see [[KAGRA/subgroup/ifo/MIF/Minutes20170410|ISC Meeting minutes 20170410]]) [Michimura] * Needs to implement frequency noise, but FSS modeling with ALS is complicated [student!] * Paper? {*} * bKAGRA Phase 1 initial alignment / commissioning plan [Michimura]: [[http://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5692|JGW-T1605692]] {*} * updated based on current schedule * ETMX and ETMY cryopayload installation almost at the same time * MICH lock at room temperature before cooling down (instead of cooling down ETMY first) * AS cannot be used for room temperature MICH lock (SR3 not ready) * SR2 won't be ready by the end of March 2018 * Fixed mirrors for AS port (including SR2) * Some comments from the Chief Meeting * Revised schedule seems compatible with PRMI. Why not? * PRMI is an option after achieving the Phase 1 goal, if it doesn't delay the final bKAGRA [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5595|JGW-T1605595]] * Initial alignment does not interfere with ITM Type-A installation work? * Evacuation of IXC/IYC compatible with Type-A installation work? * Initial alignment compatible with Pcal setup at EXA/EYA? * Meeting with Inoue on June 15 {*} * PD at EXA/EYA compatible with Pcal setup * Don't we need something like aLIGO baffle PDs for initial alignment after evacuation? Use Tcam (Pcal camera)? * IR/green steering mirrors [Michimura] (see [kagra-isc 01649]) {*} * for POP/POS and green steering in PR2/SR2 chamber, needs picomotors and ~40 cm pedestals * need this by the end of August 2017 (after PR2 installation on June, before IR initial alignment starts on September) * proposed mirror specs * HR reflectivity: more than 99% for both 1064nm and 532nm * AR refectivity: less than 0.3 % for 1064nm, similar for 532nm * incient angle: 20-45 deg, s-polarization * radius of curvature: flat * size: 2-inch * wedge: 1 deg * substrate: Fused Silica * surface quality: λ/20, 0.1 nm rms roughness See [[KAGRA/subgroup/ifo/MIF/Minutes20170410|this page]] for other agendas.