Line 2: Line 2:
Participants: Participants: Tomotada Akutsu, Yoichi Aso, Shinji Miyoki, Kiwamu Izumi, Kenta Tanaka, Chiaki Hirose, Yuta Michimura
Line 11: Line 11:
 * External Review candidate dates
  * To be determined by Densuke
 * External Review topics
  * Materials for the review will be distributed in advance of the review
  * Misunderstandings between ourselves in what is technical and what is management
  * Better to show what are the current issues recognized by ourselves and our planned means to solve them
   * With a Gantt chart including uncertain points
  * Topics for the External Review
   * Daily alignment
   * ASC commissioning and simulations
    * Including reports from the site, by Kenta Tanaka and Chiaki Hirose.
   * Gantt chart for O4 (if possible)
 * '''Action Items'''
  * Determine the review date
  * Hold a meeting to summarize current WFS commissioning/simulation situations
  * Ask what is the situation with FINESSE GUI development
Line 14: Line 31:
  *   * 2021 August 3,4,5, 10, 11, 24, 25, 26
Line 16: Line 33:
  1. How to perform the daily alignment of IFO,
  1. Simulation of WFS,
  1. How to close ASC loops during the lock acquisition process,
  1. How to use local sensors, WFS signals and BPC, etc. to enhance
stability and to minimize noise contribution.
  1. How to perform the daily alignment of IFO
   * Summary of alignment scheme in O3GK to RSE trial https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=12594
   * We can present our improvement plans and also ask for further improvements necessary
  1. Simulation of WFS
   * IMC ASC closed but with larger noise and was turned off during O3GK.
   * IFO ASC not commissioned well. Too dirty beams.
    * https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=11687
    * https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=11061
    * https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=10996
   * IFO ASC simulations so far
    * BRSE, PRFPMI, SRFPMI, FPMI https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=10359
    * PRMI, DRMI simulations necessary
   * Report on FINESSE simulation on IMC ASC by C. Hirose
   * Probably better to be reported by site people
    * What is the status of ASC simulations and commissioning? PRMI and DRMI?
    * FPMI
     * https://klog.icrr.u-tokyo.ac.jp/osl/?r=12133
     * https://klog.icrr.u-tokyo.ac.jp/osl/?r=11869
     * https://klog.icrr.u-tokyo.ac.jp/osl/?r=11641
     * https://klog.icrr.u-tokyo.ac.jp/osl/?r=11543
     * https://klog.icrr.u-tokyo.ac.jp/osl/?r=11537
  1. How to close ASC loops during the lock acquisition process
   * No idea
  1. How to use local sensors, WFS signals and BPC, etc. to enhance stability and to minimize noise contribution
   * No idea
   * Probably better to be reported by suspension commissioning team

ISC Meeting for External Review Preparations on 2021/07/13 15:00 - 16:00

Participants: Tomotada Akutsu, Yoichi Aso, Shinji Miyoki, Kiwamu Izumi, Kenta Tanaka, Chiaki Hirose, Yuta Michimura

Zoom meeting: https://zoom.us/j/6676627462

Your time zone: https://www.timeanddate.com/worldclock/fixedtime.html?iso=20210713T0600

back to Meetings page

Minutes

  • External Review candidate dates
    • To be determined by Densuke
  • External Review topics
    • Materials for the review will be distributed in advance of the review
    • Misunderstandings between ourselves in what is technical and what is management
    • Better to show what are the current issues recognized by ourselves and our planned means to solve them
      • With a Gantt chart including uncertain points
    • Topics for the External Review
      • Daily alignment
      • ASC commissioning and simulations
        • Including reports from the site, by Kenta Tanaka and Chiaki Hirose.
      • Gantt chart for O4 (if possible)
  • Action Items

    • Determine the review date
    • Hold a meeting to summarize current WFS commissioning/simulation situations
    • Ask what is the situation with FINESSE GUI development

Agenda