Line 24: Line 24:
   * https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=15840
   * https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=15865
   * https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=16104

In-vac PD/QPD layout meeting 2025/02/28

Time: Feb 28, 2025 14:00-14:40

Participants: Ray-Kuang Lee, Huali Chen, Yoichi Aso, Yuta Michimura

Zoom meeting

Minutes

  • Huali showed almost the final layout idea for AS RF and OMC REFL, with squeezing injection optics.
    • OSTM transmission seems different from CAD
      • Probably because OSTM wedge is not included in Huali's calculations
    • Add periscopes for AS RF in-vac path and OMC REFL path, and a beam diverter for AS RF in-vac path
      • Adding periscopes can reduce the height from approx. 210 mm to 4 inch, and we can use smaller and lighter pedestals
    • Check if OMC shroud is not conflicting
  • Next step is to collect comments for AS and to start REFL/POP planning
    • New student might be available
    • REFL/POP should be done by around summer
  • A/I

  • Next meeting: TBD on the week of March 24, with a new student