In-vac PD/QPD layout meeting 2025/07/29
Time: July 29, 2025 14:00-15:00
Participants: Huali Chen, Ryan Yang, Ray-Kuang Lee, Yoichi Aso, Yuta Michimura
Zoom meeting
Minutes
- In-vac periscope (Ryan)
First design based on modification of https://dcc.ligo.org/LIGO-D1201410 presented.
- Modified the direction of the beam
- Modified to use Opto-Sigma VMHG-50.8 instead of Siskiyou LIGO mirror mounts.
- Modified to have slotted holes to make it height adjustable
- Default height is 4 inch - 15 mm (baseplate thickness) for lower mirror, 210 mm for upper mirror
- Baffle hole size need to be checked to see if it is not too small or not too large compared with the beam size
- Resonant frequency need to be checked with FEM
- If too low, re-design needed (e.g. make the slotted holes short).
- POP design (Ryan)
- Used the distance of 1399 mm for in-vac POP steering mirror and HBS1 on POP table [Check]
- Found that the beam size on HBS1 (2 inch mirror) is quite large (~10 mm radius)
- POP forward beam need to be added to the layout
- In-air POP beam and green beam layout need to be updated to see if they fit in POP table
- Beam is quite elliptic although currently assuming a circular beam from PR2
Try to use qx and qy in ModeMatch wiki page for designing the telescope
- OMC chamber update (Yuta)
Periscopes and fast beam shutter (https://dcc.ligo.org/D2200426) need to be added to the CAD layout to see if they fit.
- If the fast beam shutter does not fit, OFI need to be moved towards Y-arm, and the position of ORM1 need to be re-adjusted. Note that the OFI bases are not moved.
- Base plate for RF QPD paths need to be designed.
- May be split into two so that it won't be too big for installing through the door of the OMC chamber.
- Start with 15 mm thick, and try FEM to see if this thickness is enough.
A/I
- Consult with VAC people to start designing REFL PD tank [Yuta]
- Check the resonant frequency of the in-vac periscope with FEM [Ryan]
- Double check the beam size on HBS1 [Yuta]
Try to use qx and qy in ModeMatch wiki page for designing the telescope for POP [Ryan]
- Add POP forward beam to the POP layout [Ryan]
- Add in-air POP layout and green layout [Ryan]
- Check if the in-vac periscope fits in OMC chamber layout [Ryan]
- Check if the fast beam shutter fits in OMC chamber layout, and move OFI towards Y-arm if needed [Ryan]
- Start designing the base plate for the RF QPD paths in the OMC chamber [Ryan]
Add beam diverter (https://dcc.ligo.org/LIGO-D1100642), base plate, and beam dumps to the OMC chamber layout [next step...]
- Create cable list (RF QPDs, picomotors, PZTs, beam shutter, beam diverter) for OMC chamber to see their weight for designing OMC vibration isolation table [Yuta; by the end of this year]
- Next meeting: TBD