= ISC Task Assignment Plan 2015/8/10 = A task with O mark means the assignment was confirmed == iKAGRA == === Management [Aso, Michimura] === * Finalize the task list * Assign people to the tasks * Make a schedule for iKAGRA ISC tasks -> '''Important''': to be done first === Analog Electronics (MIF, IOO, AEL) === * Complete the iKAGRA ISC electronics diagram [Michimura] O * Make a cabling plan [Michimura] O * Installation of the ISC electronics for iKAGRA [Aso, Nakano] O === Integration with the Digital Control System (MIF, IOO, DGS) === * Make a channel list for iKAGRA ISC (including whether each channel needs a whitening filter) [Kokeyama] O * Write ISC real time codes [Student + Kokeyama, Michimura] O * Create MEDM screens [Student + Kokeyama, Michimura] O * Write guardian scripts [Student + Kokeyama, Michimura] O === Cameras (AOS) === * Decide where to put cameras [Aso, Kokeyama] O * Figure out how to mount the cameras [Aso, Kokeyama] O * Test the camera server [Kokeyama, Aso] O * Buy more cameras [Aso] O * Install the cameras [Kokeyama, Aso + Students] O === Optical Layout of the REFL bench (IOO) [Toyama Univ.] === . -> '''To be confirmed''' === Initial Alignment (MIF) === * Write a document of the initial alignment procedure for iKAGRA [Michimura] △ . -> Eventhough the procedure may be changed at the site, it is important to have an official procedure and update it as we develop a better method. * Actually perform the initial alignment [Michimura + Students] O . -> Need coordination with VIS people (we need them at the site during the alignment work) === Commissioning of the Mode Cleaner (IOO) === * List up measurements to be done with iKAGRA [Kawamura + everyone] -> '''To be confirmed''' === Commissioning of the Michelson === * List up measurements to be done with iKAGRA [Aso + everyone] O === ISC Modeling (MIF, IOO) === * Build a model of iKAGRA with Chris's noise budget code [Student + Michimura] O * Make a noise budget for iKAGRA -> feed this information to the commissioning task list [Student + Michimura] O == bKAGRA == * Management [Aso, Michimura] O * Finalize the task list * Assign people to the tasks * Make a schedule for bKAGRA ISC tasks * Interferometer optical simulations (MIF) * FFT simulations with realistic mirror maps [Hirose, Hiro Yamamoto] O * Decide whether IBF is necessary or not [Aso, Hirose, Somiya, Michimura] O . -> It is related to OMC and also the control of the auxiliary DOFs. '''Aso will propose how to organize the work.''' * Requirements on the PRG, intra-cavity power, contrast defects [JANGO] O -> '''Need to specify the task more in detail''' * Thermal lensing of the MIF mirrors [JANGO] O -> '''Need to specify the task more in detail''' * ISC Modeling (MIF, IOO) * Build a model of bKAGRA with Chris's noise budget code [Students + Michimura] O * Fix the laser frequency stabilization servo design [Michimura, Aso] O * AS Port Design (IOO) * Overall design of the AS optics (after SRM) [Somiya + Students] O * OFI design [Somiya + Students] - > '''Pending''' * OMMT design [Somiya + Students] O * Steering mirrors ? [Somiya + Students] * OMC design [Somiya + Students] O * Setting OMC requirements or ITM polish requirements using simulations with real mirror maps [Somiya, Hiro Yamamoto] -> To be merged with the simulation tasks above. * Discuss with overseas groups about vibration isolation systems for OMC (and possibly other AS optics) [Somiya, Akutsu] * Other Signal Ports (IOO) -> '''To be confirmed''' * REFL table optical design [Students + Kawamura] * POP table optical design [Students + Kawamura] * POS table optical design [Students + Kawamura] * POX/POY table optical design [Students + Kawamura] * In-vac PD design [Doi, Aso] * Laser Power Management (IOO, MIF, CRY) * How to change the laser power during the operation [Students + Kawamura] -> '''To be confirmed''' * Check the compatibility of the variable laser power with cryogenics [K. Yamamoto] -> '''To be confirmed''' * Beam shutters (in-air, in-vac) [Somiya + Students] O * High power beam damps [Akutsu] -> '''To be confirmed''' * Initial Alignment (MIF) * Write a document of the initial alignment procedure for bKAGRA [Michimura] O * Lock Acquisition (MIF, IOO) * Simulation of the signals with various interferometer configurations (DRMI, PRFPMI, etc) using Optickle and Finesse (cross check) [Students + Michimura, Aso] O * Design of the ALS -> '''To be discussed with Kawamura-san'' ''''' * '''''Review the noise budget for the ALS [Students + Aso, Kawamura] ''''' * '''''Make design drawings of the ALS [Students + Aso, Kawamura] ''''' * '''''Deceide a scheme to generate f3 & f1 (AM) sidebands [Nakano, Michimura, Uehara, Somiya] ''''' . '''''-> This is probably within the scope of Nakano-kun's PhD project. '''''''To be confirmed with Kawamura-san'' * Write a document for the lock acquisition procednure [Students + Aso] O * Analog Electronics (MIF, IOO, AEL) * List up necessary ISC electronics for bKAGRA [Michimura, Aso] O * Draw an ISC electronics diagram for bKAGRA [Michimura] O * Make a cabling plan [Michimura] O * Integration with the Digital Control System (MIF, IOO, DGS) * Write ISC real time codes [Student + Kokeyama, Michimura] O * Create MEDM screens [Student + Kokeyama, Michimura] O * Cameras (AOS) * Decide where to put cameras [Aso, Kokeyama] O * Figure out how to mount the cameras [Aso, Kokeyama] O * Buy more cameras [Aso] O * Consider how to look at the cryogenic mirror surfaces (MIF, CRY) [Tomaru ?, Aso] -> '''To be discussed with Tomaru-san''' * Commissioning (MIF) * Make a commissioning plan for bKAGRA [Aso + everyone] O