⇤ ← Revision 1 as of 2018-06-08 17:39:46
541
Comment:
|
546
|
Deletions are marked like this. | Additions are marked like this. |
Line 6: | Line 6: |
Workers: Ikenoue, Simon * Measured the resonant frequencies of the NAB suspension in 5 DoFs; see [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=5205|here]]. The report itself was posted on June 7. |
* Workers: Ikenoue, Simon * Measured the resonant frequencies of the NAB suspension in 5 DoFs; see [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=5205|here]]. The report itself was posted on June 7. |
Line 9: | Line 9: |
Workers: Ikenoue, Simon, S. Saitou, Akutsu * Replaced the suspension wires and took the alignment; see [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=5196|here]] |
*Workers: Ikenoue, Simon, S. Saitou, Akutsu * Replaced the suspension wires and took the alignment; see [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=5196|here]] |
20180601
Today's activities in Mitaka
* Workers: Ikenoue, Simon
Measured the resonant frequencies of the NAB suspension in 5 DoFs; see here. The report itself was posted on June 7.
*Workers: Ikenoue, Simon, S. Saitou, Akutsu
Replaced the suspension wires and took the alignment; see here
Next plan