* Measured the resonant frequencies of the NAB suspension in 5 DoFs; see [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=5205|here]]. The report itself was posted on June 7. | * Measured the resonant frequencies of the NAB suspension in 5 DoFs; see [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=5205|here]]. The report itself was posted on June 7. |
Line 10: | Line 10: |
* Replaced the suspension wires and took the alignment; see [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=5196|here]] | * Replaced the suspension wires and took the alignment; see [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=5196|here]] |
20180601
Today's activities in Mitaka
Workers: Ikenoue, Simon
Measured the resonant frequencies of the NAB suspension in 5 DoFs; see here. The report itself was posted on June 7.
Workers: Ikenoue, Simon, S. Saitou, Akutsu
Replaced the suspension wires and took the alignment; see here
Next plan