Differences between revisions 9 and 12 (spanning 3 versions)
Revision 9 as of 2011-08-29 06:03:51
Size: 961
Comment:
Revision 12 as of 2012-06-27 16:59:07
Size: 885
Comment:
Deletions are marked like this. Additions are marked like this.
Line 1: Line 1:
= IR Pick-off and Transmit Telescopes = = Transmission Monitor =
Line 3: Line 3:

Also called as "beam reducing telescope (BRT)".
Line 4: Line 7:
'''[[../|..Up]]'''
Line 7: Line 11:
Pick-off and transmit IR beams from vacuum chambers. Transmission monitors for IR/Green beams.
Line 9: Line 13:
== Applicable Documents ==
 * Spec. for vacuum chambers
 * Optical Layout Drawing of the LCGT interferometer
 * Length Sensing and Control doc
 * Alignment Sensing and Control doc
 * CCD Monitor doc
 * Any...
Line 23: Line 20:
=== Required channels ===
For each TMS
Line 27: Line 27:
 * BS chamber
 *

== Requirements ==
TBD

== Characteristics ==
TBD
 * At the dedicated chambers in back of ETM chambers
Line 37: Line 30:
== Inspection plans ==
TBD

== Procurement process and plans ==
TBD
Line 44: Line 31:
 * [[https://dcc.ligo.org/cgi-bin/DocDB/ShowDocument?docid=62886|LIGO-E1100537-v10, Transmission Monitor Telescope Suspension (TMS) Final Design]]

Transmission Monitor

Related subgroups: IOO, MIF, VAC, CRY, VIS...

Also called as "beam reducing telescope (BRT)".


..Up

Scope

Transmission monitors for IR/Green beams.

General Description

TBD

Functions

Beams for TBD

Required channels

For each TMS

Naming Conventions

TBD

Locations

  • At the dedicated chambers in back of ETM chambers

LCGT/subgroup/AOS/BeamReduceTelescope1 (last edited 2012-09-28 03:45:15 by TomotadaAkutsu)