Differences between revisions 1 and 14 (spanning 13 versions)
Revision 1 as of 2011-09-03 08:40:40
Size: 564
Comment:
Revision 14 as of 2011-09-03 09:22:35
Size: 885
Comment:
Deletions are marked like this. Additions are marked like this.
Line 7: Line 7:
The scope of ''Initial Alignment'' is to determine the procedure and plan of setting the initial alignment of LCGT optics.
This task also includes procurement of tools required for setting the initial alignment.
The scope of ''Initial Alignment'' is to determine the procedure for initially aligning the LCGT main optics as well as the main optical paths.
This task also includes procurement of tools required for the pursuance.

== Activity Allocation ==
|| '''''Activities''''' || '''''Assinged to''''' || '''''Memo'''''||
|| Determining the procedure || MIF || ||
|| Procurement of tools || || Autocollimator?||
Line 11: Line 16:
None.
Line 14: Line 20:
This needs to be determined before the LCGT installation.

Initial Alignment

Related subgroups: MIF, IOO, VAC, CRY, VIS


Scope

The scope of Initial Alignment is to determine the procedure for initially aligning the LCGT main optics as well as the main optical paths. This task also includes procurement of tools required for the pursuance.

Activity Allocation

Activities

Assinged to

Memo

Determining the procedure

MIF

Procurement of tools

Autocollimator?

Applicable Documents

None.

General Description

It is important. This needs to be determined before the LCGT installation.

Requirements

TBD

Characteristics

TBD

Inspection plans

TBD

Procurement process and plans

TBD

LCGT/subgroup/AOS/InitialAlign1 (last edited 2012-02-10 14:47:52 by TomotadaAkutsu)