Line 20: Line 20:

 * TxPD1 repairing
  * Repaired. To be checked.
 * OFS2 closed loop functionality repairing
  * Relay is OK. Investigating the cause.
 * DAC noise problem
  * With DAC cable, very large noise and offset are observed. It may be difficult to set working point.
 * Excitation port noise
Line 30: Line 24:
 * DAC input bias between MEDM and actual
 * Laser remote control
  * Setup done. LAN cable should be replaced to shorter one.
Line 34: Line 25:
  * Tx PDs detect light even if the AOM input is almost 0.
Line 35: Line 27:
   * Borrowing 2 from Toyama univ. They has to be returned on 9/19 or 20.   * Module wall will be black coated.
Line 37: Line 29:
~9/11 ~11/3 first test to inject PCal laser to the X-end test mass
Line 39: Line 31:
 * Periscope install
  * Equip picomoters to the mirror

~10/3
 * Complete periscope install
Line 45: Line 32:

~10/20 first test to inject PCal laser to the X-end test mass
  * Rx PD done.
  * QPD alignment
Line 49: Line 35:
  * Check working point is consistent to that in KEK   * Done. To be checked periodically.
Line 51: Line 37:
  * Done.
  * OFS board gain seems strange.
  * Strange bump in AA/AI (~6 kHz)
Line 52: Line 41:
  * Modification is required from LIGO's procedure.
Line 54: Line 42:
  * To be delivered on 9/19 or 20 to Toyama Univ.
  * May have to prepare voltage calibrator to calibrate readout by DGS.
  * X-end done, but it may affected by stray light.
Line 60: Line 47:
  * Picomoter setting
Line 62: Line 48:
  * Guardian
Line 70: Line 57:
  * DGS part seems not noisy, but cause large noise when connected to the OFS.
Line 93: Line 81:
 * Periscope re-installation
Line 95: Line 85:
~Y-arm commissioning

 * Prepare cross calibration setup and calibrate an integrating sphere

Detailed task list of PCal is listed here.

X-end PCal

Urgent

  • Excitation port noise

2nd-urgent

  • Stray light
    • Tx PDs detect light even if the AOM input is almost 0.
    • Put dumpers
    • Module wall will be black coated.

~11/3 first test to inject PCal laser to the X-end test mass

  • Rx module alignment
    • Rx PD done.
    • QPD alignment
  • AOM response measurement
    • Done. To be checked periodically.
  • OL/CL TF measurement
    • Done.
    • OFS board gain seems strange.
    • Strange bump in AA/AI (~6 kHz)
  • WSK measurement
    • Code for WSK measurement analysis
    • X-end done, but it may affected by stray light.

~X-arm commissioning line injection

  • BPM test
  • Preparation for X-arm commissioning calibration line injection
    • Guardian

~O3

  • RPN measurement
  • Laser noise measurement
  • Harmonics noise measurement
  • VGA noise measurement
  • Excitation noise measurement
    • DGS part seems not noisy, but cause large noise when connected to the OFS.
  • Peak stability test
  • Shot noise
  • Offset input noise
  • Noise model
  • Unstable D-sub connection at Tx module
    • Some connectors are dead.
  • Cable arrangement
  • OFS upgrade
  • Operation tool preparation

Bonus work

  • AOM current
    • Sometimes over 0.5 V ?
  • Take care about grounding
  • Initial laser power just after turned on seems too small ?

Pre-categorization

Y-end PCal

  • Periscope re-installation

Laser power calibration setting in Toyama Univ.

~Y-arm commissioning

  • Prepare cross calibration setup and calibrate an integrating sphere