Line 20: | Line 20: |
* TxPD1 repairing * Repaired. To be checked. * OFS2 closed loop functionality repairing * Relay is OK. Investigating the cause. * DAC noise problem * With DAC cable, very large noise and offset are observed. It may be difficult to set working point. |
* Excitation port noise |
Line 30: | Line 24: |
* DAC input bias between MEDM and actual * Laser remote control * Setup done. LAN cable should be replaced to shorter one. |
|
Line 34: | Line 25: |
* Tx PDs detect light even if the AOM input is almost 0. | |
Line 35: | Line 27: |
* Module wall will be black coated. | |
Line 36: | Line 29: |
~9/11 | ~11/3 first test to inject PCal laser to the X-end test mass |
Line 38: | Line 31: |
* Periscope install * Equip picomoters to the mirror ~10/3 * Complete periscope install |
|
Line 44: | Line 32: |
~10/20 first test to inject PCal laser to the X-end test mass |
* Rx PD done. * QPD alignment |
Line 48: | Line 35: |
* Check working point is consistent to that in KEK | * Done. To be checked periodically. |
Line 50: | Line 37: |
* Done. * OFS board gain seems strange. * Strange bump in AA/AI (~6 kHz) |
|
Line 51: | Line 41: |
* Modification is required from LIGO's procedure. | |
Line 53: | Line 42: |
* To be delivered on 9/19 or 20 to Toyama Univ. * May have to prepare voltage calibrator to calibrate readout by DGS. |
* X-end done, but it may affected by stray light. |
Line 59: | Line 47: |
* Picomoter setting | |
Line 61: | Line 48: |
* Guardian | |
Line 69: | Line 57: |
* DGS part seems not noisy, but cause large noise when connected to the OFS. | |
Line 92: | Line 81: |
* Periscope re-installation |
|
Line 94: | Line 85: |
~Y-arm commissioning * Prepare cross calibration setup and calibrate an integrating sphere |
Detailed task list of PCal is listed here.
X-end PCal
Urgent
- Excitation port noise
2nd-urgent
- Stray light
- Tx PDs detect light even if the AOM input is almost 0.
- Put dumpers
- Module wall will be black coated.
~11/3 first test to inject PCal laser to the X-end test mass
- Rx module alignment
- Rx PD done.
- QPD alignment
- AOM response measurement
- Done. To be checked periodically.
- OL/CL TF measurement
- Done.
- OFS board gain seems strange.
- Strange bump in AA/AI (~6 kHz)
- WSK measurement
- Code for WSK measurement analysis
- X-end done, but it may affected by stray light.
~X-arm commissioning line injection
- BPM test
- Preparation for X-arm commissioning calibration line injection
- Guardian
~O3
- RPN measurement
- Laser noise measurement
- Harmonics noise measurement
- VGA noise measurement
- Excitation noise measurement
- DGS part seems not noisy, but cause large noise when connected to the OFS.
- Peak stability test
- Shot noise
- Offset input noise
- Noise model
- Unstable D-sub connection at Tx module
- Some connectors are dead.
- Cable arrangement
- OFS upgrade
- Operation tool preparation
Bonus work
- AOM current
- Sometimes over 0.5 V ?
- Take care about grounding
- Initial laser power just after turned on seems too small ?
Pre-categorization
Y-end PCal
- Periscope re-installation
Laser power calibration setting in Toyama Univ.
~Y-arm commissioning
- Prepare cross calibration setup and calibrate an integrating sphere