Differences between revisions 18 and 25 (spanning 7 versions)
Revision 18 as of 2018-09-20 16:18:11
Size: 2468
Comment:
Revision 25 as of 2018-10-10 17:46:40
Size: 2318
Comment:
Deletions are marked like this. Additions are marked like this.
Line 20: Line 20:

* TxPD1 repairing
  * Repaired. To be checked.
 * RxPD1 repairing
  * Repaired but not tested.
Line 24: Line 23:
  * Relay is OK. Investigating the cause.
 * DAC noise problem
  * With DAC cable, very large noise and offset are observed. It may be difficult to set working point.
  * Register is missing. To be delivered.
 * Interlock repairing
Line 30: Line 28:
 * DAC input bias between MEDM and actual
Line 36: Line 33:
~10/3
 * Complete periscope install
 * Rx module alignment
Line 42: Line 35:
 * Rx module alignment
  * After vacuuming and ETMX alignment by commissioning team.
Line 48: Line 43:
  * To be delivered on 9/19 or 20 to Toyama Univ.   * It is at Toyama Univ.

Detailed task list of PCal is listed here.

X-end PCal

Urgent

  • RxPD1 repairing
    • Repaired but not tested.
  • OFS2 closed loop functionality repairing
    • Register is missing. To be delivered.
  • Interlock repairing

2nd-urgent

  • Laser remote control
    • Setup done. LAN cable should be replaced to shorter one.
  • Stray light
    • Put dumpers

~10/20 first test to inject PCal laser to the X-end test mass

  • Rx module alignment
    • After vacuuming and ETMX alignment by commissioning team.
  • AOM response measurement
    • Check working point is consistent to that in KEK
  • OL/CL TF measurement
  • WSK measurement
    • Modification is required from LIGO's procedure.
    • Code for WSK measurement analysis
    • It is at Toyama Univ.
    • May have to prepare voltage calibrator to calibrate readout by DGS.

~X-arm commissioning line injection

  • BPM test
    • Picomoter setting
  • Preparation for X-arm commissioning calibration line injection

~O3

  • RPN measurement
  • Laser noise measurement
  • Harmonics noise measurement
  • VGA noise measurement
  • Excitation noise measurement
  • Peak stability test
  • Shot noise
  • Offset input noise
  • Noise model
  • Unstable D-sub connection at Tx module
    • Some connectors are dead.
  • Cable arrangement
  • OFS upgrade
  • Operation tool preparation

Bonus work

  • AOM current
    • Sometimes over 0.5 V ?
  • Take care about grounding
  • Initial laser power just after turned on seems too small ?

Pre-categorization

Y-end PCal

Laser power calibration setting in Toyama Univ.

PcalTask (last edited 2018-11-22 09:41:33 by chihiro.kozakai)