bKAGRA Phase2
- Target: Joining O3 with ~10Mpc of BNC.
- Term: 2018/5/7 ~ 2019/May?
Schedule
2017/5/8 updated
Stage 1
- Target: High power laser
- Term: 2018/5/7 ~ 2018/9
Stage 2
- Target: X arm commissioning
- Term: 2018/10 ~ 2018/12?
- Milestone
- VIS ITMX
- Initial alignment of X arm
- Cavity lock with IR
- Cavity lock with green
Stage 3
- Target: Y arm commissioning
- Term: 2018/12? ~ 2019/2?
- Milestone
- Replacing ETMY
- VIS and CRY of ITMY
- Initial alignment of Y arm
- Cavity lock with IR
- Cavity lock with green
Stage 4
- Target: FPMI commissioning
Stage 4
- Target: DRFPMI commissioning
Observation
- Joinning O3 of LIGO/VIRGO