Differences between revisions 1 and 6 (spanning 5 versions)
Revision 1 as of 2018-05-01 10:57:47
Size: 1597
Comment:
Revision 6 as of 2018-05-01 11:01:11
Size: 923
Comment:
Deletions are marked like this. Additions are marked like this.
Line 10: Line 10:
== Operation == == 1. Operation ==
Line 13: Line 13:
 * Duty cycle is 80-90%.
Line 16: Line 15:
== 2. Report of work of the last week and plan of work ==
Line 17: Line 17:
== 1. Report of work of the last week and plan of work ==

 * VAC:
  * Door was closed and pump down started. One large leak was found and it is being searched where it is.

 * IFO, ETMs: Enomono, Ushiba
  * Michelson fringe was seen on DC and RF, but still mirror motion is too large.
  * Needs more work for damping for both ETMs, L2P of BS.

 * DGS:
  * IO chassis of k1ioo was disconnected somehow. It is being checked now.

 * DAQ:
  * Recoding minute_raw of k1fw1 moved to SSD at k1tw1. All fw0,1 tw0,1 are working well without any gap on data.
 * IFO, ETMs: *Izumi, Enomono
  * Duty cycle is 80-90%.
Line 33: Line 21:
== 2. Operation ==

 * Noise injection needs some preparations for speakers.
 * Schnupp asymmetry need some preparations.
 * Other plan seems to be ready.
 * CBC will perform an online analysis.

Minute of KAGRA commissioning meeting


  • Date: 2018/5/1 11AM~12PM
  • Attendance: Miyakawa, Kokeyama, Aso, Miyoki, Ushiba, Tomaru
    • eZuce: Suzuki, Uchiyama, Takahaashi, Ohashi


1. Operation

  • Going well.

2. Report of work of the last week and plan of work

  • IFO, ETMs: *Izumi, Enomono
    • Duty cycle is 80-90%.

3. Tasks or discussions

  • 5/28 extend chief meeting for looking back phase 1.
  • GW alert: online alert in the control room might be prepared. -> Togoshi

Others

  • Laser power of oplev started dropping, specially lasers where are close to cryostat for year term.
  • Phase 1 summarize should talk wide range view.
    • Type A has double stable point.
    • Monitor for water level, and vacuum gage for weekend should be implemented.
    • Patrol light should be implemented soon, even manual one.
  • Next meeting: 4/24