Minute of KAGRA commissioning meeting


  • Date: 2018/6/5 11AM~12PM
  • Attendance: Miyakawa, Uchiyama, Aso, Yamamoto, Yokozawa, Enomoto, Stefan
    • eZuce: Izumi, Nakano, Inoue, Yamamoto(Toyama), Suzuki, Miyoki, Ushiba, Eleonora, Shoda, Tegoshi


0. Schedule

  • k1ix0 will be needed by September for NAB PD.

1. X arm commissioning

  • JGW-T1808343

  • Do we need WFS?(Eleonora) -> Yes, with control system.(Kiwamu)

2. New 40 W laser

3. PMC electronic hack

Others

  • Next meeting: 5/29.